Sl.No Title Consultant Agencies PI of Project  Value of Project
Rs. in Lakhs 
Status
1 Proof Checking of Structural Items of Rambili Project Suvadra Consultant Dr. S R Dash                         14.95 On-going
2 Vetting of second floor structure of CESU building for additional load IDCO Dr. B Hanumantha Rao                           1.87 On-going
3 Mix Design for WMM & GSB with optimum utilisation of granulated slag Tata Steel Ltd Dr. U C sahoo                           1.15 On-going
4 Characterisation of soils treated with Zydex products for its use in PMGSY Roads Zydex Industries (P) Ltd Dr. U C Sahoo                           2.30 On-going
5 Dyke hight raising of Fly-Ash pond Vedanta Ltd Dr. B Hanumantha Rao                           6.74  Approved
6 Proof checking of major bridge @ Ch 1+445 of NH-149 pallahara to Pitiri Section, Odisha RKD Construction (P) Ltd Dr. S R Dash                           1.73 On-going
7 Vetting of design and drawings of aranya bhavan 6th floor conference room  IDCO Dr. B Hanumatha Rao                           1.50 Completed
8 Structural stability for the building with revised loading conditions of 2nd floor level with its retrofitting actions NBCC (I) Ltd. Dr. Sumanta Halder                           8.00 On-going
9 Vetting of the AFS Hanger at Bagdogra, super structure drawing (Steel Structure) M/s MES Engineering, Kolkata Dr. Goutam Mondal                           1.75 On-going
10 Third party sudit on the fly ash generation & utilization by TPPs in Odisha for the year 2015-16 M/s State Pollution control Board Dr. B hanumatha Rao                           2.59 Approved
11 Proof Checking of Design Splice & its adequacy by M/s S M Consultancy for 30m FOB girder Rail Vihar Nigam Ltd. Waltair Dr. S R Dash                           0.41 On-going
12 Monitoring and quality assurance of construction of international standard sport climbing wall at kalinga stadium, BBSR Outdoor School Dr. Sumanta Halder                           7.10 On-going
13 Proof checking of design and drawing of substructure for 16 nos of major bridges of RVNL Rail Vihar Nigam Ltd. BBSR Dr. S R Dash                           9.06 On-going
14 Testing pf CC cores of RE Facia Panel NHAI, PIU-BBSR Dr. U C Sahoo                           1.73 On-going
15 Safety consultancy for construction of new road at the missing link portion of NH81 along the approved alignment between Harischandrapur and eastern approach of kalindri - bridge from Km 46.550 to km59.697 in the district of Malda, West Bengal on EPC mode Dynamic Projects (P) Ltd Dr. P P Dey                           2.30 On-going
16 Proof checking of design and drawings of substructure for 6 nos of major bridges of RVNL Rail Vikas Nigam Ltd Dr. S R Dash 2.16 On-going
17 Quality test of Railway track stone (Gudiakateni & Chandikhol) Jyoti Construction Dr. U C sahoo 0.30 Completed
18 Development of structural grade concretes utilizing Iron slag as sand replacements (Tata Steel, Jaipur, Odisah) Tata Steel, Kalinga Nagar Dr. Dinaka Pasla 5.74 Completed
19 Proof checking of design and drawing of substructure and foundation abutment-2 of bridge no -76 Rail Vikas Nigam Ltd Dr. S R Dash 0.86 Completed
20 Vetting of Structural design and drawing of the Dinjan Hanger foundation LLOYD Insulations Ltd Dr. Goutam Mondal 0.30 Completed
21 Technical support on pile design in L iquefiable soils for the building at the Sewage Treatment Plant (Tunasan STP) Vatech Wabag Ltd Dr. S R Dash 2.88 On-going
22 Proof checking of structural calculation/ drawing for proposed construction of JNV/ Nayagarh (Phase-B) works at Odisha Buildsol, Architectural & Engineering Consultants Dr. S R Dash 0.65 Completed
23 Widening and strengthening of Khunti-Torpa-Kolebira Road (from 0.00 km to 82.055 km) to 2-lane with paved shoulder to work as safety consultancy Gawar-S.C.C. (JV), Rahtak, Haryana Dr. P P Dey 3.52 On-going
24 Mix design for glass fibre reinforced concrete for IMDC Mancheswar, Bhubaneswar NBCC, Bhubaneswar Dr. Dinakar Pasla 1.64 On-going
25 Vetting of feasibility study of pre-treatment of coke oven and by-product plant effluent in coal gasification process units for recovery of Phenol and Ammonia Jindal Steel and Power Limited Dr. P Bhunia 5.75 Completed
26 Proof checking of design and drawing of road under bridge (RUB) No-68 of RVNL Rail Vikas Nigam Ltd, Rail Vihar Dr. S R Dash 0.36 Completed
27 Widening and strengthening from km 94.000 to 131.000 of NH-133 in the state of Jharkhand through EPC Basis contract – as safety consultant Gawar-S.C.C. (JV), Rahtak, Haryana Dr. P  P Dey 1.59 Completed
28 Mix Design for M25 for Mahanadi Institute of medical sciences and research at Talcher , Angul, Odisha NBCC, Talcher Dr. Dinakar Pasla 3.11 On-going
29 Mix Design of M30 Grade Concrete for ITC Hotel Prime Techno Engineers (P) Ltd. Dr. Dinakar Pasla 0.45 On-going
30 Proof checking of design and drawing for 2 nos of S&T Cabin building for M/S NTPC at Kaniha RITES Ltd Dr. S R Dash 0.72 On-going
31 Proof checking of design and drawing of substructure for major bridges no 115 and 131 Rail Vikas Nigam Ltd, Rail Vihar Dr. S R Dash 1.15 Completed
32 Testing of Panels for energy absoption test ILFS SIF Dr. Dinakar Pasla                           2.86 Completed
33 Testing of light weight aggregates (LWAs) in various concrete grades and the physical and chemical testing of the aggregates and also the structural load behaviour of the LWA concretes Jindal Steel and Power Limited Dr. Dinakar Pasla                           5.64 On-going
34 Proof Checkin of Design and Drawing of Substructure of Railway Bridge of RVNL Rail Vikas Nigam Ltd, Rail Vihar Dr. S R Dash                           0.86 Completed
35 Vetting of structure and superstructure of sports climbing facility at Kalinga Stadium confirming to IFSC standard Outdoor School Dr. Sumanta Halder                           4.09 Completed
36 Stability study of the ash filled area Vedanta Limited Dr. B hanumatha Rao                           3.14 Completed
37 Design and Drawing for Katekela Lagoon-2 ash pond  Vedanta Limited Dr. B hanumatha Rao 8.19 Completed
38 Strenghthening and Widening/ Reconstruction of Dumka Masalia-Nala upto West Bengal Border Road lane with paved shoulder under EPC Mode (55 km) Barbrik_RCPL(JV) Dr. P P Dey                           2.36 On-going
39 Design of experimental road using fly ash Sesa Sterlite Limited Dr. B hanumatha Rao 3.078 Completed
40 Technical Evaluation of cement concrete roads in Odisha Planning & Coordination Dept., Govt. of Odisha Dr. U C sahoo                         28.16 On-going
41 Technical Scrutiny of irrigation road proposal under IRC & IS Water Reseources Dept., Govt. of Odisha Dr. U C sahoo                           4.26 Completed
42 Improvement and upgradation of two lane with paved shoulder configurationof Koderma-Domchanch-Khorimahua-Jamua Road (SH-13) under EPC mode in Jharkhand NIT Durgapur Dr. P P Dey                           2.00 On-going
43 Conducting Mix Design for M50 for NBCC Bhubaneswar NBCC Ltd Dr. Dinakar Pasla                           1.33 Completed
44 Geotechnical investigations on soil/rock samples NBCC Ltd Dr. B hanumatha Rao                           1.20 Completed
45 Testing of Ballast from Baghua Querry Maa Chandi Stone Crushing Dr. S R Dash                           0.17 Completed
46 Surge analysis for 1000mm Dia water rising main at Jajpur IDCO Dr. Arindam Sarkar                           1.90 Completed
47 Proof checking of srtructural design nad drawing Hindustan steel works construction Ltd. Dr. S R Dash                           0.43 Completed
48 Design and analysis for making rural road about 1 km by using JK Paper Mills fly ash JK Papers Mills Limited Dr. B Hanumatha Rao                           2.85 Completed
49 Assessment of structural safety of construction of balance six floor of the IDCOL corporate office building, BBSR IDCO Dr. Sumanta Halder                         12.64 Completed
50 Testing of materials and conducting design mix M-25,M-30 & M-40 in connection with construction of commercial cum residential complex  National Building construction corporation Ltd. Dr. P Bhunia                           4.38 Completed
51 Opinion regarding the dri reduction furnace at JSPL plant Angul Kazstroy Services SIF Pvt. Ltd Dr. Dinakar Pasla                           2.81 Completed
52 Assessing the soil for earth work construction IVRCL Limited Dr. B hanumatha Rao                           0.53 Completed
53 Testing of AAC Blocks Overtop marketing (P) Ltd. Dr. Dinakar Pasla                           3.07 Completed
54 Testing of AAC Blocks Fast Build Blocks Pvt. Ltd Dr. Dinakar Pasla                           0.77 Completed
55 Vetting/checking of the project report prepared by CEMCPL for Ordnance Factory, Ambajhari, Nagpur Centre for Envotech and Management Consultancy (P) Ltd Dr. R R Dash                           1.40 Completed
56 Testing of Fibre shorcrete panels for energy absorption test Leighton India Contractors (P) Ltd Dr. Dinakar Pasla                           4.68 Completed
57 Design and stability analysis of an embankment for new BG rail line from Haridaspur to Paradeep in the Khurda district Odisha Tracks & Tower Infratech (P) Ltd  Dr. Hanumatha Rao                           3.65 Completed
58 Testing of Fibre shorcrete panels for energy absorption test Leighton India Contractors (P) Ltd Dr. Dinakar Pasla                           5.26 Completed
59 Issue of Check Proof Certificate and Procedure for the rectification of FOB along with necessary drawing regarding McML-ECI(JV) Dr. S R Dash                           1.26 Completed
60 Assessment of High Compressibility of cut spoil Tracks & Tower Infratech (P) Ltd  Dr. B hanumatha Rao                           1.26 Completed
61 Widening & Strengthening of Bhawanipatna-Gunupur-Kasipur Road (SH-44) to 2 Lane without paved shoulder from Km 0/000 to 13/000 & Km 42/940 to Km 48/840 on EPC mode in the district of Kalahandi Office of the Executive Engineer Koraput (R&B) Division Dr. B hanumatha Rao                           0.50 Completed
62 Vetting of structural Design and Drawing for the Construction of L.I.G and L.M.I.G housing Complex along with Commercial Complex at Kalinga Nagar Zone- K4 BDA Dr. S R Dash  -  Cancelled
63 Impact Assessment study of city bus services operational under JnNURM Housing and Urban Development Department, Govt of Odisha Dr. Debasis Basu                           6.98 Completed
64 Proof Checking of POT cum PTFE Bearing Bhubaneswar Expressways Pvt. Ltd Dr. Dinakar Pasla                           1.01 Completed
65 Design and testing aerated autoclaved fly concrete blocks (AAC) Fast Build Blocks Pvt. Ltd Dr. Dinakar Pasla                           1.18 Completed
66 Consultancy for investigation in ARC, Charbatia Airports Authority of India, Biju Pattanaik Airport Dr. Dinakar Pasla                         13.49 Completed
67 Proof checking of design and drawing of three no. box bridges under Railway loading in connection with construction of railway siding to serve Koderma Thermal Power Plant (2x500MW) of DVC RITES Ltd Dr S C Dutta 3.79 Completed
68 Database for Principal Technical Agency & State Technical Agency for states of Jharkhand and odisha NRRDA Dr U C Sahoo 42.72 On-going
69 Design of two number of 220KV transmission line tower foundations between Kantapalli to Hindalco in the mahanadi river Hindalco
Industries Ltd.
Dr. Arindam Sarkar                           7.18 Completed
70 Proof Checking of design of pile foundations for location no. 16A and 24 of 220 KV transmission line tower from Bidanasi ( Cuttack) near the bank of Kathajodi to Nuapada (Cuttack) in the spill zone Orissa Power
Transmission
Corporation Limited
Dr. Sumanta Halder                           2.27 Completed
71 Vetting of structural analysis of design and drawing for the new residential complex at HAL Koraput HAL Prof. S C Dutta                           5.00 Completed
72 Proof Checking of design of river bed pile foundation for location no. 10,12 & 15 of 220KV transmission line from Bidanasi to Cuttack grid substation Orissa Power
Transmission
Corporation Limited
Dr. Sumanta Halder                           3.31 Completed
73 Preparation of special Foundation for 220KV Tower for Two locations(158-c & 159)  Hindalco
Industries Ltd.
Dr. Arindam Sarkar                           4.84 Completed
74 Proof Checking od 3 Nos panel cabin building and 1 no. gate lodge/IBS Building for M/s. Nalco Angul RITES Ltd Dr. Dinakar Pasla                           0.60 Completed
75 Remedial Measures for Horizontal and vertical
Cracks Developed in the walls, floors, roof etc of ESI Hospital, Jaykaypur
ESI Corporation Dr. Dinakar Pasla                           3.95 Completed
76 Vetting of the design of lighting masts and their foundations in connections with commissioning of lighting systems of wankahade stadium Bajaj Electricals Ltd. Prof. S.C. Dutta                           1.10 Completed