Sl.No | Title | Consulting Agencies | PI of Project | School | Value of Project Rs. in Lakhs |
Duration of the project | Start Date | End Date | Code | Status |
---|---|---|---|---|---|---|---|---|---|---|
578 | Peer review of structural design for trident vasa project at Kalinga Nagar, Bhubaneswar | TRIDENT PROPERTIES PRIVATE LIMITED | Dr. B Hanumantha Rao | SIF | 12.61 | One Year | 3-Jan-24 | 2-Jan-25 | CP578 | On-going |
577 | Vetting of structural design and drawings of BFP related reinforced concrete buildings located at Berhampur | Shiv Construction Co. | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.30 | One Months | 6-Jan-24 | 5-Feb-24 | CP577 | On-going |
576 | Vetting of Hydraulic and structural design for execution of rural piped water supply project pertaining to 149 villages of Tangi-Chowdar block of Cuttack district. | BHUGAN INFRACON PRIVATE LIMITED | Dr. Arindam Sarkar | SIF | 7.01 | One Year | 4-Jan-24 | 3-Jan-25 | CP576 | On-going |
575 | Vetting of civil structural documents, electrical process, mechanical and instrumentation design and drawing of 3 Nos Individual Rural Piped water supply projects pertaining to Koraput and Navarangapur Districts | Larsen and Toubro - Infrastructure Vertical | Dr. Srinivas Bhaskar Karanki | SES | 27.44 | Six Months | 6-Jan-24 | 5-Jul-24 | CP575 | On-going |
574 | Vetting of traffic density study for Environmental clearance of proposed Enhancement in iron ore production from Sandspur Iron & Manganese Mines of M/s National Enterprises At: Village-Sanindpur, Tehsil-Koida, Dist Sundargarh, Odisha | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED | Prof. Rajesh Roshan Dash | SIF | 0.77 | Ten Days | 23-Nov-23 | 3-Dec-23 | CP574 | On-going |
573 | Vetting of traffic density study for Environmental clearance of proposed M/s Utkal Health Care Private Limited Plot No.C/3 Niladri Vihar, Chandrasekharpur, Bhubaneswar Odisha | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED | Prof. Rajesh Roshan Dash | SIF | 0.77 | Ten Days | 21-Dec-23 | 31-Dec-23 | CP573 | On-going |
572 | Vetting of Nallah Diversion Plan for Kuraloi-A North Coal Mines of M/s Vedanta Ltd (Volume-1) prepared by CEMC Pvt Ltd, Bhubaneswar | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED, | Prof. Rajesh Roshan Dash | SIF | 0.94 | One Month | 19-Dec-23 | 18-Jan-24 | CP572 | On-going |
571 | Vetting of project report for amendment of Environmental clearance of M/s XIM University | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED | Prof. Rajesh Roshan Dash | SIF | 0.77 | Two Weeks | 9-Nov-23 | 23-Nov-23 | CP571 | On-going |
570 | Vetting of Design of Automatic Wheel Wash | GLOBALTECH ENVIRO EXPERTS PRIVATE LIMITED | Prof. Rajesh Roshan Dash | SIF | 1.00 | One Month | 28-Dec-23 | 27-Jan-24 | CP570 | On-going |
569 | Mix design verification for construction of statue at Varanasi | M/s MATU RAM ART CENTRES PRIVATE LIMITED | Prof. Dinakar Pasla | SIF | 2.36 | One Month | 29-Dec-23 | 28-Jan-24 | CP569 | On-going |
568 | Proof checking of one minor bridge at Kusmunda open cast of Kusmunda area, Korba (CG) | RITES LTD | Prof. S K Panda | SIF | 0.94 | One Month | 4-Oct-23 | 3-Nov-23 | CP568 | On-going |
567 | Testing of concrete core samples for two major bridges at Naupada | EXECUTIVE ENGINEER R&B DIVISION KHARIAR | Prof. Dinakar Pasla | SIF | 1.18 | One Months | 11-Dec-23 | 10-Jan-24 | CP567 | On-going |
566 | Fragility of different types of offshore wind turbines in seismic conditions | Renew Risk | Prof. Sumanta Haldar | SIF | 3.68 | One Month | 22-Dec-23 | 21-Jan-23 | CP566 | On-going |
565 | Vetting & proof checking of Structural Drawings & design of 1 00 seater Boys Hostel at six locations in the district of Angul, Staff quarters for REB Sub Division Rairakhol, Sambalpur and Pabitra mohan Smrutipitha at Palhara, Angul | M/S NBSP CONSULTANTS PRIVATE LIMITED | Prof. Sarat Kumar Panda | SIF | 3.54 | Six Months | 26-Dec-23 | 25-Jun-24 | CP565 | On-going |
564 | Power factor improvement study | PARADEEP PHOSPHATES LTD. | Prof. C.N.Bhende | SES | 7.67 | Four Months | 15-Dec-23 | 14-Apr-24 | CP564 | On-going |
563 | Vetting of electrical and E&M designs and drawings pertaining to the Jajpur District | KALPATARU PROJECTS INTERNATIONAL LIMITED | Dr. Srinivas Bhaskar Karanki | SES | 3.39 | Six Months | 18-Dec-23 | 17-Jun-24 | CP563 | On-going |
562 | Vetting of electrical and E&M designs and drawings pertaining to the Angul District | KALPATARU PROJECTS INTERNATIONAL LIMITED | Dr. Srinivas Bhaskar Karanki | SES | 3.69 | Six Months | 1-Nov-23 | 30-Apr-24 | CP562 | On-going |
561 | Vetting of electrical and E&M designs and drawings pertaining to the Nayagarh District | KALPATARU PROJECTS INTERNATIONAL LIMITED | Dr. Srinivas Bhaskar Karanki | SES | 3.54 | Six Months | 10-Nov-23 | 9-May-24 | CP561 | On-going |
560 | Vetting of structural design and drawings for sliding gate for 40 mtrs length | Prasur Electricals and Engineering Co. | Prof. S K Panda | SIF | 1.18 | Three Months | 14-Dec-23 | 13-Mar-24 | CP560 | On-going |
559 | Vetting of Structural design and drawing of construction for LCSS Building of MSP Plant at IREI, Matikhalo, Chatarapur, Ganjam, Odisha | INSTRUMENT & CONTROL | Prof. S K Panda | SIF | 1.00 | Three Months | 15-Dec-23 | 14-Mar-23 | CP559 | On-going |
558 | Establishment off Chair Professor in Cyber Security | WHIZHACK TECHNOLOGIES PRIVATE LIMITED | HoS SES | SES | 23.36 | Three Years | 18-Nov-23 | 17-Nov-26 | CP558 | On-going |
557 | Audit of ash disposal and utilization of NAVA Limited | M/S.NAVA LIMITED | Dr. B Hanumantha Rao | SIF | 1.11 | Two Weeks | 12-Dec-23 | 26-Dec-23 | CP557 | On-going |
556 | Audit of ash disposal and utilization of IMFA Limited | M/S. INDIAN METALS & FERRO ALLOYS LIMITED | Dr. B Hanumantha Rao | SIF | 1.11 | Three Months | 4-Dec-23 | 3-Mar-24 | CP556 | On-going |
555 | Testing of filter bed sand material | KALPATARU PROJECTS INTERNATIONAL LIMITED | Dr. B Hanumantha Rao | SIF | 1.59 | Six Months | 9-Oct-23 | 8-Apr-23 | CP555 | On-going |
554 | Mix design for ovehead tank | SJK Engineering Services | Prof. Dinakar Pasla | SIF | 0.80 | Two Months | 7-Nov-23 | 6-Jan-24 | CP554 | On-going |
553 | Design check of VUP for four laning of NH6 in Odisha, Sambalpur | ALAM CONSTRUCTIONS | Prof. Sumanta Haldar | SIF | 4.72 | One Month | 5-Dec-23 | 1-Apr-24 | CP553 | On-going |
552 | Proof checking of stuructural design of DDM (Deputy Director of Mines) office and laboratory at 04 sites for Odisha Mining Corporation (OMC) | CREATIVE ARCHITECTS COMBINE PRIVATE LIMITED | Prof. S K Panda | SIF | 2.36 | Six Months | 5-Dec-23 | 4-May-23 | CP552 | On-going |
551 | Mix design and Bridge design vetting for Vedanta Ltd Lanjigarh | MAHAVIR ENGINEERING | Prof. Dinakar Pasla | SIF | 1.77 | One Month | 23-Nov-23 | 23-Dec-23 | CP551 | Completed |
550 | Proof checking design and drawings of minor bridges, box culverts and hume pipe culverts | M/S KEC INTERNATIONAL LTD. | Dr. Jothi Saravanan Thiyagarajan | SIF | 6.58 | Two Months | 12-Dec-23 | 11-Feb-24 | CP550 | On-going |
549 | Checking of design of process tower and boiler chimney at Somnathpur Industrial area, Balasore | IFB AGRO INDUSTRIES LIMITED | Prof. Sumanta Haldar | SIF | 5.90 | One Month | 1-Dec-23 | 31-Dec-23 | CP549 | On-going |
548 | Structural Audit of minor bridges and LVUP for development of six lane Badakumari-Karki section from km 204+000 to km 226+500 | MEHROTRA BUILDCON PRIVATE LIMITED | Dr. Jothi Saravanan Thiyagarajan | SIF | 2.66 | One Months | 1-Dec-23 | 31-Dec-23 | CP548 | On-going |
547 | Audit of ash disposal and utilization of Jindal Steel & Power Limited | JINDAL STEEL & POWER LTD | Dr. B Hanumantha Rao | SIF | 1.11 | Six Months | 1-Dec-23 | 31-May-24 | CP547 | On-going |
546 | Structural health assessment of existing 4 Lane Panikoili-Rimuli section of NH-215 (New NH-20) in Odisha | PROJECT DIRECTOR PROJECT IMPLEMENTATION UNIT KEONJHAR | Dr. Jothi Saravanan Thiyagarajan | SIF | 7.38 | One Months | 29-Nov-23 | 28-Dec-23 | CP546 | Completed |
545 | Proof checking of structural design and drawings for Factory Building at Greater Noida, Science Centre at Kota and Karbi Bhawan, at Dwarka, New Delhi | M/S SURYA FRESH FOODS LTD. | Prof. S K Panda | SIF | 3.54 | Three Months | 24-Nov-23 | 23-Feb-24 | CP545 | On-going |
544 | Proof checkingg of structural design and drawings for BDL Jhansi | VASTUNIDHI (PROP. ANIL BANSAL) | Prof. S K Panda | SIF | 2.95 | Three Months | 28-Nov-23 | 27-Feb-24 | CP544 | On-going |
543 | Groundwater and soil sample analysis | FINANCE & ACCOUNTS DEPT A M U ALIGARH | Dr. Syed Hilal Farooq | SIF | 2.99 | Three Months | 29-Nov-23 | 29-Feb-24 | CP543 | On-going |
542 | Rut Test for BC-2 Grade HMA with CRMB 60 | DCC INFRA PROJECTS LIMITED | Dr. Anush K Chandrappa | SIF | 1.18 | One Months | 29-Nov-23 | 28-Dec-23 | CP542 | On-going |
541 | Proof checking of design and drawings of Multi Story office building for Chennai Customs Audit & Chennai Import Commissionerate | SRI BALAJI CONSTRUCTIONS | Dr. Jothi Saravanan Thiyagarajan | SIF | 5.50 | Two Months | 30-Nov-23 | 31-Jan-24 | CP541 | On-going |
540 | Proof checking of Design and Drawings of Box culverts, Minor bridges, Flyovers and Light vehicular underpassess for NH-57, Odisha | MS INFRA ENGINEERS PRIVATE LIMITED | Dr. Jothi Saravanan Thiyagarajan | SIF | 12.98 | Two Months | 29-Nov-23 | 28-Jan-24 | CP540 | On-going |
539 | Vetting of structural design and drawings for construction of Bypass to Nayagarh town from km 235.469 to km 252.48 of NH-57 in the State of Odisha on EPC mode. | ROTRANS INFRA PROJECTS PRIVATE LIMITED | Prof. S K Panda | SBS | 1.48 | One Month | 20-Nov-23 | 19-Dec-23 | CP539 | On-going |
538 | Assessing the degradable matter from polypropylene and evaluating cylo toxicity of degradable matter. | RAREAN FLUID-TECH PRIVATE LIMITED | Prof. Umaprasana Ojha | SBS | 4.78 | One Year | 23-Nov-23 | 22-Nov-24 | CP538 | On-going |
537 | Assessment of quality of some Indian coals | EASTERN COALFIELDS LTD | Dr. Remya Neelancherry | SIF | 2.42 | Two Weeks | 21-Nov-23 | 5-Dec-23 | CP537 | On-going |
536 | Determination of physical characterstics of filter media for water supply projects in Odisha | M/s GVPR ENGINEERS LIMITED | Prof. Sumanta Haldar | SIF | 1.65 | Two Weeks | 7-Nov-23 | 21-Nov-23 | CP536 | On-going |
535 | Proof checking of strengthening of PSC girders between CTC-BRAG up | RAIL VIKAS NIGAM LIMITED | Prof. Dinakar Pasla | SIF | 2.95 | Three Months | 3-Nov-23 | 2-Feb-24 | CP535 | On-going |
534 | Vetting of report on Traffic analysis and pavement design report (R1) | M/S BEKEM INFRA PROJECTS PVT LTD | Dr. B Hanumantha Rao | SIF | 1.77 | Four Months | 14-Nov-23 | 13-Feb-24 | CP534 | On-going |
533 | Proof checking of Design and Drawings of Sub structure and Foundations of rail bridge having span of 6x45.7m Steel Girder over Bheden River | RITES Ltd (Bhubaneswar) | Dr. Jothi Saravanan Thiyagarajan | SIF | 7.38 | One Months | 17-Nov-23 | 16-Dec-23 | CP533 | On-going |
532 | Proof checking of general arrangement drawings and structural design of solar water pump structures | M/S S. Pallavi | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.15 | One Month | 18-Nov-23 | 17-Dec-23 | CP532 | Completed |
531 | Proof checking of Design and Drawing of pier and Pile foundation for pier P8 and P9 for ROB (1x 24.0m) over existing railway lines near Kirandul yard for NMDC Ltd. | RITES Ltd (Bhubaneswar) | Dr. Suresh R Dash | SIF | 2.95 | Four Months | 8-Nov-23 | 7-Mar-24 | CP531 | On-going |
530 | Geotechnical testing of soil samples | M/S KUMAR CREATIONS PVT LTD | Dr. B Hanumantha Rao | SIF | 0.18 | One Year | 5-Apr-23 | 4-Apr-24 | CP530 | On-going |
529 | Geotechnical testing of soil samples | M.S.ENTERPRISE | Dr. B Hanumantha Rao | SIF | 0.22 | One Year | 1-Aug-23 | 31-Jul-24 | CP529 | On-going |
528 | Geotechnical testing of 5 numbers of soil samples | ANS CONSTRUCTIONS PRIVATE LIMITED | Dr. B Hanumantha Rao | SIF | 0.44 | One Year | 20-Apr-23 | 19-Apr-24 | CP528 | On-going |
527 | Proof checking of General Arrangement Drawings of Pre-Engineered Building for Amabale Industrial and Logistics Parks | M/S INTERARCH BUILDING PROD.PVT.LTD. | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.46 | Three Weeks | 30-Oct-23 | 20-Nov-23 | CP527 | Completed |
526 | Proof checking of General Arrangement Drawings of Pre-Engineered building for Maval Industrial and Logistic Park | M/S INTERARCH BUILDING PROD.PVT.LTD. | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.42 | Three Weeks | 30-Oct-23 | 20-Nov-23 | CP526 | Completed |
525 | Proof checking of General Arrangement Drawings of Pre-engineered Building for RAR Infra & Retail LLP | M/S INTERARCH BUILDING PROD.PVT.LTD. | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.45 | Three Weeks | 30-Oct-23 | 20-Nov-23 | CP525 | Completed |
524 | Materials for improvement of minig operations (Hqdroqels and nano composites) | INNOCULE MATERIALS AND ADDITIVES PRIVATE LIMITED | Dr. Umaprasana Ojha | SBS | 7.17 | One Year | 28-Oct-23 | 27-Oct-24 | CP524 | On-going |
523 | Peer review of Plant/non-plant buildings | TRACTEBEL ENGINEERING PVT LTD | Dr. Shantanu Patra | SIF | 3.78 | Two Months | 25-Oct-23 | 24-Dec-23 | CP523 | On-going |
522 | Audit on compliance to ash generation and utilization | JINDAL INDIA THERMAL POWER LIMITED | Dr. B Hanumantha Rao | SIF | 1.11 | Four Months | 25-Oct-23 | 24-Feb-24 | CP522 | On-going |
521 | Feasibility of EOT crane for hangar at Bhubaneswar | GE (N&CG) Bhubaneshwar | Prof. Sumanta Haldar | SIF | 14.16 | Five Months | 10-Oct-23 | 9-Mar-24 | CP521 | On-going |
520 | Inspection and testing of welding of steel plate girders at site (Patna, Bihar) and fabrication yard (Rewari, Haryana) | SENIOR PROJECT ENGINEER, WORKS DIVISION PATNA-1, BIHAR RAJYA PUL NIRMAN NIGAM LTD. | Prof. M M Mahapatra | SMS | 5.16 | Six Months | 25-Oct-23 | 24-Apr-24 | CP520 | On-going |
519 | Strutural audit of civil works for development of six lane Badakumari-Karki section of NH-130-CD road under Raipur-Viskhapatnam Economic Corridor | UMSL LTD | Dr. Jothi Saravanan Thiyagarajan | SIF | 2.66 | One Months | 25-Oct-23 | 24-Nov-23 | CP519 | Completed |
518 | Vetting of detailed basic engineering package, drawing including P&ID, layout of packaged plants. | GRACE GREEN INFRA PRIVATE LIMITED | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.36 | Three Weeks | 17-Oct-23 | 7-Nov-23 | CP518 | Completed |
517 | Vetting of structural design and drawings for Construction of Bypass Road to Balangir town from Km 72.400 (Design Km 0.000) to Km 79.800 (Design Km 11.670) of NH-26 in the State of Odisha on EPC mode | ROTRANS INFRA PROJECTS PRIVATE LIMITED | Prof. S K Panda | SIF | 12.98 | One Month Three Weeks | 16-Oct-23 | 5-Dec-23 | CP517 | On-going |
516 | Conducting a feasibility study on utilization of OB material of Kulda OCP for various Civil constuction purposes | MAHANADI COALFIELDS LIMITED. | Prof. Sumanta Haldar | SIF | 35.55 | Three Month and Two Weeks | 6-Oct-23 | 19-Jan-24 | CP516 | On-going |
515 | Vetting of DPRs for Road Projects developed under BDA | M/S SHREE JAGANNATH CONSULTANCY | Dr. U C Sahoo | SIF | 1.77 | One Month | 5-Oct-23 | 4-Nov-23 | CP515 | Completed |
514 | Proof checking of general arrangement drawings and structural design of ROB bearing chainage 87+482 | R&C INFRAENGINEERS PRIVATE LIMITED | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.31 | One Month | 30-Sep-23 | 30-Oct-23 | CP514 | Completed |
513 | Design/quality analysis of constructed 04 nos double storied building at different places of subarnapur district | VIGILANCE DIRECTORATE ORISSA CUTTACK | Dr. Suresh R Dash | SIF | 4.47 | Two Weeks | 5-Oct-23 | 19-Oct-23 | CP513 | On-going |
512 | Vetting of distribution network pertaining to scheme to 30 GP of Kuchinda and Bamra block of Sambalpur district | M/S LASER POWER & INFRA PRIVATE LIMITED | Dr. Arindam Sarkar | SIF | 5.50 | One Month | 29-Sep-23 | 28-Oct-23 | CP512 | Completed |
511 | Biostratigraphic and Sedimentological evaluation of Mahanadi basin using drilling records | OIL INDIA LTD | Dr. Raj Kumar Singh | SEOCS | 11.20 | Six Months | 11-Oct-23 | 10-Apr-24 | CP511 | On-going |
510 | Assessment of quality of some Indian coals | EASTERN COALFIELDS LTD | Dr. Remya Neelancherry | SIF | 3.66 | Two Weeks | 28-Sep-23 | 12-Oct-23 | CP510 | On-going |
509 | Proof checking of general arrangement drawings of Pre-engineered building (Mahindra & Mahindra) | M/S INTERARCH BUILDING PROD.PVT.LTD. | Dr. Jothi Saravanan Thiyagarajan | SIF | 3.69 | One Month | 20-Sep-23 | 19-Oct-23 | CP509 | Completed |
508 | Structure vetting for Mahadev Greens at Trisulia Cuttack the total built-up area 46,129 sqm (496350 sqft) | MAHADEV GRIHA NIRMAN PRIVATE LIMITED | Prof. S K Panda | SIF | 11.81 | Two Months | 27-Sep-23 | 26-Nov-23 | CP508 | On-going |
507 | Proof checking of design and drawings of four lane ROB and its approaches in lieu of existing level crossing at kesinga in the state of Odisha | RAJLAXMI CONSTRUCTIONS LIMITED | Prof. S K Panda | SIF | 5.90 | Two Months | 14-Sep-23 | 13-Nov-23 | CP507 | On-going |
506 | Proof checking of structural design and drawings of high-rise building | STALWART PROJECTS PRIVATE LIMITED | Dr. Jothi Saravanan Thiyagarajan | SIF | 7.08 | One Month | 27-Sep-23 | 26-Oct-23 | CP506 | Completed |
505 | Integration and analysis of advanced machine learning algorithms with LACOS codebase | INDO-KOREA SCIENCE AND TECHNOLOGY CENTER | Dr.Debi Prasad Dogra | SES | 25.77 | One Year | 26-Sep-23 | 25-Sep-24 | CP505 | On-going |
504 | Mix design for construction of Technical buildings at Vizag for MES | GOPAL TEKNOCON PRIVATE LIMITED | Prof. Dinakar Pasla | SIF | 1.18 | Two Months | 29-Aug-23 | 28-Oct-23 | CP504 | Completed |
503 | Structural vetting for Acreplex Bhubaneswar | ACREPLEX REALTY PRIVATE LIMITED | Prof. Dinakar Pasla | SIF | 14.16 | Two Months | 29-Aug-23 | 28-Oct-23 | CP503 | Completed |
502 | Proof checking of new auction hall and commercial building for Paradip fishing harbor | INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. Devesh Punera | SIF | 5.90 | One Month | 1-Sep-23 | 30-Sep-23 | CP502 | On-going |
501 | Vetting of the technical report on carrying out hill protection work near type-VE quarters at Mandala, Anushaktinagar, Mumbai | GABION TECHNOLOGIES INDIA PRIVATE LIMITED | Dr. B Hanumantha Rao | SIF | 1.11 | Six Months | 15-Sep-23 | 14-Mar-24 | CP501 | On-going |
500 | Verification of elevated service reservoir on precast basis for execution of 2 nos of individual rural pipe water suply project | M/S KEC INTERNATIONAL LTD. | Prof. Sumanta Haldar | SIF | 1.18 | Three Weeks | 7-Sep-23 | 30-Sep-23 | CP500 | On-going |
499 | Bituminous Mix Designs for Resurfacing of Runway at Biju Patnaik Int. Airport, Bhubaneswar | JKG INFRATECH PRIVATE LIMITED | Dr. U C Sahoo | SIF | 4.78 | Two Months | 12-Sep-23 | 11-Nov-23 | CP499 | On-going |
498 | Development of foundation design and drawings for 220kv & 440kv towers in wind zone VI | M/s ODISHA POWER TRANSMISSION CORPORATION LTD | Prof. Sumanta Haldar | SIF | 10.00 | Five Months | 13-Sep-23 | 12-Feb-24 | CP498 | On-going |
497 | Traffic Studies on PWD Roads in Odisha | EXECUTIVE ENGINEER PROJECT IMPLEMENTATION UNIT OSRP | Dr. Umesh C Sahoo | SIF | 230.10 | Seven Months | 5-Sep-23 | 4-Apr-24 | CP497 | On-going |
496 | Job Mix Formula (JMF) for Full Depth Reclamation (FDR) of PMGSY Roads in Jharkhand Misc PIUs | Chief Engineer, JSRRDA, Jharkhand, Ranchi | Dr U C Sahoo | SIF | 11.80 | Six Months | 11-Aug-23 | 10-Feb-24 | CP496 | On-going |
495 | Proof checking of structural design and drawings for 'Construction of new Campus for Indian Institute of Foreign Trade (IIFT) at Kakinada, Andhra Prasdesh | D.K. & ASSOCIATES | Prof. S K Panda | SIF | 3.54 | Two Months | 2-Sep-23 | 1-Nov-23 | CP495 | Completed |
494 | Proof check of bridge works at Lajkura | INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. Devesh Punera | SIF | 1.77 | One Month | 31-Aug-23 | 30-Sep-23 | CP494 | On-going |
493 | Proof check of bridge works of SECL | INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. Devesh Punera | SIF | 2.36 | Seven Weeks | 31-Aug-23 | 19-Oct-23 | CP493 | On-going |
492 | Site visit and suggestion for bank slope failure at 147 km to 149 km of TGRL-TKMA doubling project | RAIL VIKAS NIGAM LIMITED | Dr. Santoshkumar G | SIF | 0.71 | Two Weeks | 14-Aug-23 | 28-Aug-23 | CP492 | Completed |
491 | Vetting and proof checking of structural drawings and design of District Audit Office at Angul | M/S NBSP CONSULTANTS PRIVATE LIMITED | Dr. Jothi Saravanan Thiyagarajan | SIF | 0.94 | Three Weeks | 31-Aug-23 | 21-Sep-23 | CP491 | Completed |
490 | Vetting of propoed pipeline alignment and placement of valves with regards to water hammer effect, surge protection analysis | M/S ORISSA INDUSTRIAL INFRACTURE DEVELOPMENT CORPORATION | Dr. Arindam Sarkar | SIF | 4.85 | One Month | 30-Aug-23 | 29-Sep-23 | CP490 | Completed |
489 | Vetting and proof checking of structural drawings and design of HFL bridges | M/S SHIV SHAKTI ENGINEERING WORKS. | Dr. Jothi Saravanan Thiyagarajan | SIF | 4.01 | One Month | 25-Aug-23 | 24-Sep-23 | CP489 | Completed |
488 | Proof checking of structural design and drawings of structure with built area 7504 sqm | M/S VICTOR COMPONENT SYSTEMS PLTD | Prof. S K Panda | SIF | 1.23 | Two Months | 18-Aug-23 | 17-Oct-23 | CP488 | Completed |
487 | Proof checking of desing and drawings of civil structures pertaining to Bari & Korei Block of Jajpur District | KALPATARU PROJECTS INTERNATIONAL LIMITED | Dr. Jothi Saravanan Thiyagarajan | SIF | 17.26 | Six Months | 22-Aug-23 | 21-Nov-23 | CP487 | On-going |
486 | Proof checking of desing and drawings of civil structures pertaining to Gania, Dasapala and Nuagaon Block in Nayagarh District | KALPATARU PROJECTS INTERNATIONAL LIMITED | Dr. Jothi Saravanan Thiyagarajan | SIF | 18.14 | Six Months | 22-Aug-23 | 21-Nov-23 | CP486 | On-going |
485 | Proof checking of design and drawings of civil structures pertaining to Banarpal and Angul Blocks in Angul District | KALPATARU PROJECTS INTERNATIONAL LIMITED | Dr. Jothi Saravanan Thiyagarajan | SIF | 20.21 | Six Months | 22-Aug-23 | 21-Nov-23 | CP485 | On-going |
484 | Proof checking of Hanumanji statue at Nathdwara | SMB CORPORATION OF INDIA | Prof. Dinakar Pasla | SIF | 3.00 | Two Months | 4-Aug-23 | 3-Oct-23 | CP484 | Completed |
483 | Proof checking of structural design and drawings of hostel building | VASTUKAR (PROP-SOUMYENDU SHANKAR RAY) | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.12 | Three Weeks | 8-Aug-23 | 1-Sep-23 | CP483 | Completed |
482 | Structural stability check for the project building of G+1 at Khariar, Nuapada District | RG CIVIL CONSULTANTS | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.48 | Two Weeks | 11-Aug-23 | 25-Aug-23 | CP482 | Completed |
481 | Proof check of major bridge no.10 and 28 for the work "Development of railway infrastructure upto 4 MTPA plant expansion" of Vedanta Ltd. Lanjigarh | INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. Devesh Punera, Assistant Professor | SIF | 7.08 | One Month | 2-Aug-23 | 1-Sep-23 | CP481 | Completed |
480 | Mix design for construction of Technical building at Binnaguri | CHHABINDRA KUMAR PRADHAN C/o GE(S) Binnaguri | Prof. Dinakar Pasla | SIF | 1.18 | Two Months | 2-Aug-23 | 1-Oct-23 | CP480 | Completed |
479 | Mix design for construction of substructure at Chandipur for MES | M/s LIRA CONSTRUCTIONS PRIVATE LIMITED, C/o MES Chandipur, Odisha | Prof. Dinakar Pasla | SIF | 1.18 | Two Months | 13-Jul-23 | 12-Sep-23 | CP479 | Completed |
478 | Design of cement concrete pavements for six FCI Depot in Odisha | FOOD CORPORATION OF INDIA | Dr U C Sahoo | SIF | 11.80 | Six Months | 21-Jul-23 | 20-Jan-24 | CP478 | Completed |
477 | Request for proposal (RFP) for road work for Deendayal Port Authority (DPA) | GLOBAL ARCHER CONSTRUCTION AND ENGINEERING LLP | Prof. Dinakar Pasla | SIF | 5.90 | One Month | 25-Jul-23 | 24-Aug-23 | CP477 | On-going |
476 | Proof checking of structural design and drawings for Institutional Building on Plot No: 1-15, Wish Town, Sector 128, Jaypee Greens, Noida. | M/s Wish Town Towers LLP | Prof. S K Panda | SIF | 1.23 | Three Weeks | 24-Jul-23 | 14-Aug-23 | CP476 | Completed |
475 | Environmental Assessment Study for issue of No Increase in pollution load certificate for proposed Bitumen Unit of 832 TMTPA Capacity at Paradip Refinery | M/s Indian Oil Corporation Limited | Dr. Rama Krushna Sabat, Assistant Professor | SMMME | 5.43 | Three Months | 24-Jul-23 | 23-Oct-23 | CP475 | On-going |
474 | Vetting of the technical report of engineering solution of slope stablization work at project-Bengaluru-Salem section | GABION TECHNOLOGIES INDIA PRIVATE LIMITED | Dr. B Hanumantha Rao | SIF | 1.11 | Three Weeks | 16-Jul-23 | 8-Aug-23 | CP474 | On-going |
473 | Fitness monitoring system & pro dignostics of LURO BURNER | PARADEEP PHOSPHATES LTD. | Dr. Venugopal Arumuru | SMS | 14.57 | Six Months | 18-Jul-23 | 17-Jan-24 | CP473 | On-going |
472 | Proof checking of structural design and drawings for Factory Building on Plot No:-A-119/1,Sector-29,Yamuna Expressway,Distt. Gautam Buddh Nagar,Up | SURYA GLOBAL FLEXIFILMS PRIVATE LIMITED | Prof. S K Panda | SIF | 4.91 | Three Weeks | 19-Jul-23 | 9-Aug-23 | CP472 | Completed |
471 | Carrying out the Third Party Quality Assurance Consultancy (TPQAC) for the Construction and Development of Kendriya Vidyalaya School at Siddipet, Telangana | VADDI BOINA PRASADA REDDY | Prof. Dinakar Pasla | SIF | 8.00 | One Year | 22-Jul-23 | 21-Jul-24 | CP471 | On-going |
470 | Proof checking of structural design and drawing of a multi-storeyed building proposed at Bhubaneswar, Odisha | FORTUNE INFRAPROPERTIES PRIVATE LIMITED | Prof. S K Panda | SIF | 4.30 | One Month | 18-Jul-23 | 17-Aug-23 | CP470 | Completed |
469 | Proof checking of desing and drawings of civil structures in Puri | M/S SPACE CUBE | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.59 | Three Weeks | 3-Jul-23 | 24-Jul-23 | CP469 | Completed |
468 | Proof checking of design of structural Glazing for AIIMS Bhubaneswar project. | ARCHIFABS | Dr. Jothi Saravanan Thiyagarajan | SIF | 2.21 | Three Weeks | 12-Jul-23 | 2-Aug-23 | CP468 | Completed |
467 | Proof checking of structural design and drawing for project " Proposed Lachit Moidam Memorial complex a Lahdoigarh, Jorhat" Assam | Design Associates Inc | Prof. S K Panda | SIF | 2.36 | Three Weeks | 10-Jul-23 | 31-Jul-23 | CP467 | Completed |
466 | Proof checking of 02 nos of major bridges In connection with construction of railway siding at Mahespur, Dhanbad, Jharkhand | RITES LTD | Prof. S K Panda | SIF | 2.36 | One Month | 3-Jul-23 | 2-Aug-23 | CP466 | Completed |
465 | Mix design for construction of officers married accomodation for NAVY at Visakhapatnam | RAGHUSONS INFRA ENGINEERING PRIVATE LIMITED, | Prof. Dinakar Pasla | SIF | 1.18 | Two Months | 12-Jun-23 | 11-Aug-23 | CP465 | Completed |
464 | Mix design for shotcrete for slope protection works at JODA | KADTECH GEOINFRA PRIVATE LIMITED | Prof. Dinakar Pasla | SIF | 1.18 | Three Months | 9-Jun-23 | 8-Sep-23 | CP464 | Completed |
463 | Structural healtth assessment for the up-gradation project-Duburi-Chandikhole (Pkg-III) section | NATIONAL HIGHWAYS AUTHORITY OF INDIA PIU DHENKANAL | Dr. Jothi Saravanan Thiyagarajan | SIF | 14.99 | One Month | 23-Jun-23 | 23-Jul-23 | CP463 | On-going |
462 | Proof check of new signal buildingg at Paradip | INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. Devesh Punera | SIF | 4.72 | One Month | 23-Jun-23 | 23-Jul-23 | CP462 | On-going |
461 | Proof checking of design and drawing of POT & PTFE bearing of major bridge No.2, Bridge No.4 | INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. Devesh Punera, | SIF | 3.54 | Three Weeks | 16-Jun-23 | 7-Jul-23 | CP461 | Completed |
460 | Structural health assessment for the up-gradation project-Cuttack-Angul (Pkg-I) section | NATIONAL HIGHWAYS AUTHORITY OF INDIA PIU DHENKANAL | Dr. Jothi Saravanan Thiyagarajan | SIF | 14.99 | One Month | 19-Jun-23 | 18-Jul-23 | CP460 | On-going |
459 | Structural health assessment for the up-gradation project-Cuttack-Angul (Pkg-II) section | NATIONAL HIGHWAYS AUTHORITY OF INDIA PIU DHENKANAL | Dr. Jothi Saravanan Thiyagarajan | SIF | 14.99 | One Month | 19-Jun-23 | 18-Jul-23 | CP459 | On-going |
458 | Proof checking of Bridges in connection with construction of railway siding at load out system near Laxman project at Gevra area, Korba | RITES LTD | Prof. S K Panda | SIF | 2.91 | One Month | 9-Jun-23 | 8-Jul-23 | CP458 | Completed |
457 | Proof checking of six RCC Box Bridges of Rungta Mines Limited | RUNGTA MINES LTD | Dr. Suresh R Dash | SIF | 5.52 | One Month | 8-Jun-23 | 7-Jul-23 | CP457 | Completed |
456 | Structural Vetting of Engineering, procurement and construction of Precision Engineering building and facilities for precision Engineering complex at Bhubaneswar (Odisha) | SHREEJI INFRASTRUCTURE INDIA PRIVATE LIMITED | Prof. Sarat Kumar Panda | SIF | 5.90 | One Month | 3-Jun-23 | 2-Jul-23 | CP456 | Completed |
455 | Mix design for AIIMS Bhubaneswar Critical care block | URC CONSTRUCTION PRIVATE LIMITED | Prof. Dinakar Pasla | SIF | 1.18 | Two Months | 26-May-23 | 25-Jul-23 | CP455 | Completed |
454 | Carrying out the Third Party Quality Assurance Consultancy (TPQAC) for the Construction and Development of Kendriya Viadyalaya School at Angul, Odisha | NARAYAN KUMAR INFRASTRUCTURE PVT LTD C/o NPCC Ltd | Prof. Dinakar Pasla | SIF | 8.00 | One Year | 15-May-23 | 14-May-24 | CP454 | On-going |
453 | Design of SCC for IISER Berhampur | M/s DALMIA CEMENT (BHARAT) LIMITED | Prof. Dinakar Pasla | SIF | 1.18 | One Month | 11-May-23 | 10-Jun-23 | CP453 | Completed |
452 | Utilization of red mud in concrete composites | M/S VEDANTA LIMITED ALUMINIUM & POWER | Prof. Dinakar Pasla | SIF | 17.70 | Seven Months | 18-May-23 | 17-Dec-23 | CP452 | Completed |
451 | Proof check to the desing drawings for a short span RCC T-beam structure under 19BRTF project | Lamnekha Construction Pvt. Ltd | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.99 | Two Weeks | 15-May-23 | 31-May-23 | CP451 | Completed |
450 | Mix design for Construction of Technical Building at Chandipur | CHHABINDRA KUMAR PRADHAN | Prof. Dinakar Pasla | SIF | 1.18 | Two Month | 6-May-23 | 5-Jul-23 | CP450 | Completed |
449 | Mix design for construction of MES Building at Chandipur | M/s LIRA CONSTRUCTIONS PRIVATE LIMITED, | Prof. Dinakar Pasla | SIF | 1.18 | One Month | 1-May-23 | 31-May-23 | CP449 | Completed |
448 | Proof checking of Bridges in connection with construction of railway siding at Jhanjra OCP near UKHRA station | RITES LIMITED | Prof. S K Panda | SIF | 5.37 | Two Months | 10-May-23 | 9-Jul-23 | CP448 | Completed |
447 | Proof checking of minor steel girder bridge proposed across GAIL pipeline of Naini Coal Mines,Odisha | The Singareni Collieries Company Limited | Prof. S K Panda | SIF | 0.83 | One Month | 6-May-23 | 5-Jun-23 | CP447 | Completed |
446 | Proof checking of minor bridges for proposed railway siding at Sogra Railway Station under Chakradharpur division | SHIVA CEMENT LIMITED | Prof. S K Panda | SIF | 4.60 | One Month | 9-May-23 | 8-Jun-23 | CP446 | Completed |
445 | Checking of design for soil improvement using PVD for East Coast Railway | RKIPL-KVRECPL-SKC JV | Prof.Sumanta Haldar, Professor | SIF | 1.77 | One Month | 26-Apr-23 | 25-May-23 | CP445 | Completed |
444 | Detailed technical opinion on mobile manugacturing parts " Display assempbly, fullfit scren and connectors" | OPPO MOBILES INDIA PVT. LTD. | Dr. Barathram Ramkumar | SES | 0.75 | Two Weeks | 9-May-23 | 23-May-23 | CP444 | On-going |
443 | Mix design for construction of critical care hospital block AIIMS Bhubaneswar | URC CONSTRUCTION PRIVATE LIMITED | Prof. Dinakar Pasla | SIF | 1.18 | Two Months | 27-Apr-23 | 26-Jun-23 | CP443 | Completed |
442 | Structural vetting of superstructure of 18m span ROB for additional load due to proposed pipeline | M/s PIR Projects and Consultancy Private Limited | Dr. Suresh R Dash | SIF | 2.43 | One Month | 24-Apr-23 | 23-May-23 | CP442 | Completed |
441 | Proof checking of structural design and drawing of the worker's hostel at Rourkela, Chodwar and Chhatabar under SCDF | Infrastructure Development Corporation Of Odisha Ltd. | Dr. Suresh R Dash | SIF | 13.95 | Two Months | 27-Apr-23 | 26-Jun-23 | CP441 | On-going |
440 | Proof checking of launching schemes for ROB at 245+923 (Bimalgarh)- 60m Bow string Girder | RKD CONSTRUCTION PVT LTD. | Dr. Suresh R Dash | SIF | 2.07 | Three Weeks | 17-Apr-23 | 8-May-23 | CP440 | Completed |
439 | Design and development of specialised BLDC Motors | Alphasine Technologies Private Limited | Dr. Ankit Dalal | SES | 1.50 | One Year | 20-Apr-23 | 19-Apr-24 | CP439 | Completed |
438 | Designing of Algorithms for pedestrian attribute learning and recognition | Korean Institute of Science and Technology | Dr. Debi Prosad Dogra | SES | 24.75 | Ten Months & Fifteen Days | 19-Apr-23 | 18-Feb-24 | CP438 | Completed |
437 | Vetting of structural design and drawing of T-beam bridge with pile foundation at Koah Nala at Kahalgaon, Bihar | CUBE ENGITECH CONSULTANT PVT LTD | Prof. S K Panda | SIF | 3.53 | One Month | 15-Apr-23 | 14-May-23 | CP437 | Completed |
436 | Stabilization of Soil using Cement & Novocrete at JSW Utkal Steel Ltd, Paradeep | NOVOCRETE INDIA PRIVATE LIMITED | Dr. U C Sahoo | SIF | 2.39 | Three Months | 13-Apr-23 | 12-Jul-23 | CP436 | On-going |
435 | Proof checking of 2RCC Box culvert and RCC Apron for ballast less track at private siding of M/s HPCL on Raipur-Titlagarh Section | RITES LTD | Dr. Suresh R Dash | SIF | 2.07 | Two Weeks | 11-Apr-23 | 25-Apr-23 | CP435 | Completed |
434 | Technical proof checking of Design & drawing of various component of RWSS-projects | NCC Limited | Dr. Puspendu Bhunia | SIF | 29.50 | Six Months | 11-Apr-23 | 10-Oct-23 | CP434 | On-going |
433 | Carrying out Environmental Audit of Smelter Plant, NALCO and issue of no increase in pollution load certificate | NATIONAL ALUMINIUM CO. LTD. | Dr. Manaswini Behera | SIF | 4.13 | Two Months | 30-Mar-23 | 29-May-23 | CP433 | Completed |
432 | Design of Cement Concrete Pavement for FCI depot at Khurda Road | FOOD CORPORATION OF INDIA | Dr. Umesh C Sahoo | SIF | 2.36 | Three Months | 30-Mar-23 | 29-Jun-23 | CP432 | Completed |
431 | Vetting of Project Report for amendment of environmental clerance of Shyam Metalics & Engergy Limited | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED, | Dr. Rajesh Roshan Dash | SIF | 0.77 | Ten Days | 30-Mar-23 | 9-Apr-23 | CP431 | On-going |
430 | Remedial measures to be taken for repairing PSC Girder No-17 of Railway Bridge over the IOCL Pipeline AT MMLP-Paradip (Odisha) | AMULYA KUMAR DASH | Dr. Goutam Mondal | SIF | 3.69 | Three Months | 31-Mar-23 | 30-Jun-23 | CP430 | Completed |
429 | Mix designs for BHEL Talcher | RDC CONCRETE INDIA PRIVATE LIMITED | Prof. Dinakar Pasla | SIF | 2.50 | Two Months | 14-Mar-23 | 13-May-23 | CP429 | Completed |
428 | Carrying out the Third Party Quality Assurance Consultancy (TPQAC) for the construction and development of Kendriya Vidyalaya School at Kakinada Andhra Pradesh | M/s Saroj Construction | Prof. Dinakar Pasla | SIF | 8.00 | One Year | 10-Mar-23 | 9-Mar-24 | CP428 | On-going |
427 | Proof checking of structural design and drawing of the bridge across simuli nallah, Keonjhar | EXECUTIVE ENGINEER, N.H. DIVISION, KEONJHAR | Dr. Suresh R Dash | SIF | 5.02 | One Month | 21-Mar-23 | 20-Apr-23 | CP427 | Completed |
426 | Residual stress measurement in welded pipes and plates | M/S TATA STEEL LIMITED | Prof. M M Mahapatra | SMS | 11.55 | Seven Months | 27-Mar-23 | 26-Oct-23 | CP426 | On-going |
425 | Structural adequacy of the existing plants (1,2,3) and dam administrative building | GLOBAL LAB MATERIAL TESTING PRIVATE LIMITED | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.48 | Two Weeks | 23-Mar-23 | 6-Apr-23 | CP425 | Completed |
424 | Structural Design Suggestion for restoration of P8 and strengthening of P9 and P11 of Belabahali Major Bridge LHS at Km 35+341 of New NH-20, Odisha | Bloom Companies, LLC | Dr. Suresh R Dash | SIF | 6.64 | Two Months | 6-Mar-23 | 5-May-23 | CP424 | Completed |
423 | Rut Test for DBM-2 Grade HMA | DCC INFRA PROJECTS LIMITED | Dr. Anush K Chandrappa | SIF | 1.18 | One Month | 3-Mar-23 | 2-Apr-23 | CP423 | On-going |
422 | Vetting of structural design and drawing of G+7 storied (Block-A) and B+G+4 (Block-B) Hotel and Convention centre of MAYFAIR Sanctuary | M/S MAYFAIR HOTELS & RESORTS LTD. | Prof. S K Panda | SIF | 14.99 | Two Months | 10-Mar-23 | 9-May-23 | CP422 | Completed |
421 | Carrying out The Third Party Quality Assurance Consultancy (TPQAC) for the Construction and Development of Kendriya Vidyalaya School at Balasore district, Odisha | Singhal Enterprises C/o NPCC Ltd | Dr. Dinakar Pasla | SIF | 8.00 | One Year | 23-Feb-23 | 22-Feb-24 | CP421 | On-going |
420 | Proof checking of Elevated service Reservoir on precast basis at Dharmasala, Rasulpur & Danagadi | M/S KEC INTERNATIONAL LTD. | Prof. Sumanta Haldar | SIF | 1.50 | One Month | 27-Feb-23 | 30-Mar-23 | CP420 | Completed |
419 | Stabilization of Soil using Etonis 1400S for application in Road Pavements | Wacker Chemie India Private Limited | Dr. U C Sahoo | SIF | 2.95 | Two Months | 17-Feb-23 | 16-Apr-23 | CP419 | Completed |
418 | Proof checking of design and drawings for the three lane bridge over railway track between Mancheswar-Vanivihar | M/s RAIL VIKAS NIGAM LIMITED | Dr. Dinakar Pasla | SIF | 2.50 | Three Months | 4-Feb-23 | 3-May-23 | CP418 | Completed |
417 | Proof checking of Design and Drawing of POT PTFE Bearings for ROB at MCL Talcher | RKD INFRA C/o RITES Ltd Bhubaneswar | Dr. Suresh R Dash | SIF | 3.54 | One Month | 14-Feb-23 | 13-Mar-23 | CP417 | On-going |
416 | Testing of steel samples collected from various stel plants | CHIEF ENGINEER RD & QP (R&B) BBSR | Dr. Soobhankar Pati | SMMME | 4.78 | Two Weeks | 4-Feb-23 | 18-Feb-23 | CP416 | Completed |
415 | Scrutiny of Chimney design calculations & Drawings (For WHRB & CFBC Chimneys) | MGM MINERALS LIMITED | Dr. B Hanumantha Rao | SIF | 0.81 | Three Weeks | 1-Feb-23 | 21-Feb-23 | CP415 | On-going |
414 | Durability Testing of Soil Stabilised with Soil Tech MK III as per IRC: SP 89 (PART-II)-2018 | Polymer Pavements India LLP | Dr. U C Sahoo | SIF | 1.59 | Two and Half Month | 2-Feb-23 | 17-Apr-23 | CP414 | Completed |
413 | Mix design for SCC for SCB Medical College Cuttack | Larsen and Toubro - Infrastructure Vertical | Dr. Dinakar Pasla, Associate Professor | SIF | 3.54 | Three Months | 30-Jan-23 | 29-Apr-23 | CP413 | Completed |
412 | Proof checking of desing and drawing of 1 x 11.65m RCC Slab Bridge | ISC PROJECTS PVT LTD | Dr. Suresh R Dash | SIF | 2.95 | Three Weeks | 24-Jan-23 | 14-Feb-23 | CP412 | On-going |
411 | Development of Drone System for Cleaning High Rise Buildings & for spraying Pesticides | SUN FIBO TECHNOLOGY PRIVATE LIMITED | Dr. Yogesh Ganpat Bhumkar | SMS | 1.07 | One Year | 22-Jan-23 | 21-Jan-24 | CP411 | On-going |
410 | Proof checking of Design and Drawing of substructure for elevated double track viaduct at GUA Railway station Jharkhand | RITES Ltd (Bhubaneswar) | Dr. Suresh R Dash | SIF | 23.05 | Eight Months | 18-Jan-23 | 17-Sep-23 | CP410 | On-going |
409 | Structural adequacy of existing water tank for 1.5m and 3m steel pole on top | JHAMUNA TOWER TECH PRIVATE LIMITED | Dr. Jothi Saravanan Thiyagarajan | SIF | 1.48 | Two Weeks | 13-Jan-23 | 27-Jan-23 | CP409 | Completed |
408 | Proof checking of structural design of Lube Hub (34x75m) in size for foundation and superstructure | M/s CREATIVE STUDIO | Dr. Devesh Punera | SIF | 1.18 | One Month | 9-Jan-23 | 9-Feb-23 | CP408 | Completed |
407 | Structural vetting of RCC culvert bridges, and station buildings | M/s PIR Projects and Consultancy Private Limited | Dr. Goutam Mondal | SIF | 6.93 | Fourteen Months | 7-Jan-23 | 6-Mar-24 | CP407 | On-going |
406 | Vetting of Ardent GHG Emission Report | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED, | Dr. Rajesh Roshan Dash | SIF | 0.77 | Two Weeks | 27-Dec-22 | 10-Jan-23 | CP406 | Completed |
405 | Carrying out The Third Party Quality Assurance Consultancy (TPQAC) for the construction and development of Kendriya Vidyalaya School at Vyasnagar, Jajpur District, Odisha | NARAYAN KUMAR INFRASTRUCTURE PVT LTD C/o NPCC Ltd | Dr. Dinakar Pasla | SIF | 8.00 | One Year | 26-Dec-22 | 25-Dec-23 | CP405 | On-going |
404 | Mix design of DBM and DAC of Hirasar Airport, Rajkot | YASHNAND ENGINEERS AND CONTRACTORS PRIVATE LIMITED | Dr. Anush K Chandrappa | SIF | 1.18 | One Month | 31-Dec-22 | 30-Jan-23 | CP404 | On-going |
403 | Design of SCC for the Construction of Parshuramji Statue at Arunanchal Pradesh | M/s Vipra Foundation | Dr. Dinakar Pasla | SIF | 3.00 | Two Months | 21-Dec-22 | 20-Feb-23 | CP403 | Completed |
402 | Mix design for Bridge work of East Coast Railway, Jajpur | TRENZET INFRA PRIVATE LIMITED C/o East Coast Railway, Jajpur | Dr. Dinakar Pasla, Professor | SIF | 2.95 | Three Months | 29-Oct-22 | 28-Jan-23 | CP402 | Completed |
401 | Carrying out The Third Party Quality Assurance Consultancy (TPQAC) for the construction and development of Kendriya Vidyalaya School at Dharmagard, Kalahandi, Odisha | M/S- BAISHNAB CHARAN NAYAK C/o NPCC Ltd | Dr. Dinakar Pasla | SIF | 8.00 | One Year | 15-Dec-22 | 14-Dec-23 | CP401 | Completed |
400 | Mix Design of BSM using RAP and BitChem Tailor Made Cold Binder/Emulsion for NH-2, Bardhaman, WB | BITCHEM ASPHALT TECHNOLOGIES LTD. | Dr. U C Sahoo | SIF | 1.18 | Five Weeks | 16-Dec-22 | 20-Jan-23 | CP400 | On-going |
399 | Characterization of Polymer and Crumb Rubber Modified Bitumen | BITCHEM ASPHALT TECHNOLOGIES LTD. | Dr. Anush K Chandrappa | SIF | 3.19 | Two Months | 15-Dec-22 | 14-Feb-23 | CP399 | Completed |
398 | FOS measurement of tailings dams-2021 of Vedanta Limited, Lanjigarh | M/S VEDANTA LIMITED ALUMINIUM & POWER | Dr. B Hanumantha Rao, Associate Professor | SIF | 6.05 | One Year | 8-Dec-22 | 7-Dec-23 | CP398 | On-going |
397 | Design of ground improvement work in connection with RoB in MCHP area of Paradip Port Authority, Odisha | INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. B Hanumantha Rao, Associate Professor | SIF | 2.21 | One Month | 9-Dec-22 | 8-Jan-23 | CP397 | On-going |
396 | Analog CMOS circuit design | MARQUEESEMI INDIA PRIVATE LIMITED | Dr. Nijwm Wary, Assistant Professor | SES | 4.80 | One Year | 7-Dec-22 | 6-Dec-23 | CP396 | Completed |
395 | Review of the Road Structure Design of the Perimeter Road at Rambilli near Visakhapatna | Director General Naval Projects | Dr. U C Sahoo, Assistant Professor | SIF | 3.07 | Two Months | 21-Nov-22 | 20-Jan-23 | CP395 | On-going |
394 | Mix designs for Township at Chhattisgarh | JMC PROJECTS (INDIA) LIMITED | Dr. Dinakar Pasla | SIF | 7.38 | Six Months | 30-Nov-22 | 31-May-23 | CP394 | Completed |
393 | Mix design for construction of deparmtnetal building for Postal department at Cuttack | A B INFRA PROJECTS, C/o Depatment of Post, Cuttack | Dr. Dinakar Pasla | SIF | 1.18 | Two Months | 5-Nov-22 | 4-Jan-23 | CP393 | Completed |
392 | Construction of Plant roads, drains, culverts and truck parking | TALCHER FERTILIZERS LIMITED C/o RCF Limited | Dr. B Hanumantha Rao | SIF | 2.36 | Two Months | 24-Nov-22 | 23-Jan-23 | CP392 | On-going |
391 | Design of internal road witthin RMP for mud transport | M/S. UTKAL ALUMINA INTERNATIONAL LTD. | Dr. B Hanumantha Rao, Assistant Professor | SIF | 5.32 | Two Months | 29-Nov-22 | 28-Jan-23 | CP391 | On-going |
390 | Vetting of Electrical and E&M Designs and Drawings of Nayagarh Project | M/s GVPR ENGINEERS LIMITED | Dr. Srinivas Bhaskar Karanki, SES | SES | 4.43 | Nine Months | 23-Nov-22 | 22-Aug-23 | CP390 | On-going |
389 | Proof checking of a single storey building | M/S GODGRACE INFRASTRUCTURE AND CO | Dr. B Hanumantha Rao, Assistant Professor | SIF | 1.03 | Three Weeks | 15-Nov-22 | 4-Dec-22 | CP389 | On-going |
388 | Geotechnical investigation and Foundation Design System at DRI, SMS 1&2 and CPP Project site | MGM MINERALS LIMITED | Dr. B Hanumantha Rao, Associate Professor | SIF | 1.25 | One Month | 15-Nov-22 | 14-Dec-22 | CP388 | On-going |
387 | Design verifications of security wall | M/s LIRA CONSTRUCTIONS PRIVATE LIMITED, C/o MES Chandipur, Odisha | Dr. Dinakar Pasla, Professor | SIF | 1.18 | Two Months | 10-Nov-22 | 10-Jan-23 | CP387 | Completed |
386 | Design of PQC for MES Chandipur | M/s LIRA CONSTRUCTIONS PRIVATE LIMITED, C/o MES Chandipur, Odisha | Dr. Dinakar Pasla, Professor | SIF | 1.18 | Two Months | 9-Nov-22 | 9-Jan-23 | CP386 | Completed |
385 | Proof checking of 2 Nos. of Bridges at MCL Sardega | M/s RITES Limited | Dr. Suresh R Dash | SIF | 3.98 | One Month | 29-Oct-22 | 28-Nov-22 | CP385 | Completed |
384 | Repair/Re-erection Decision of 50m SS Tower at AIR, Puri | PRASAR BHARATI BROADCASTING CORPORATION OF INDIA | Dr. Goutam Mondal | SIF | 4.43 | Four Months | 27-Oct-22 | 26-Feb-23 | CP384 | On-going |
383 | Technical report on new SW RMF: Pollution load to the first level aquifer and site location of the new RMF unit | M/S VEDANTA LIMITED ALUMINIUM & POWER | Dr. B Hanumantha Rao, Assistant Professor | SIF | 4.97 | One and Half Month | 14-Oct-22 | 28-Nov-22 | CP383 | On-going |
382 | Proof Checking for the construction of 132 Nos Type II Quarters at Old Kalyan Mandap in Unit VIII and 84 nos Type IV Quarter near old AG Colony, in Unit IV, Bhubaneswar | SHREEJIKRUPA PROJECT LIMITED | Dr. Goutam Mondal | SIF | 16.23 | Three Months | 20-Oct-22 | 19-Jan-23 | CP382 | On-going |
381 | Carrying out the vetting of warehouse of Coca Cola Beverages Pvt Ltd Khorda | RATNA INFRASTRUCTURES | Dr. Dinakar Pasla, Associate Professor | SIF | 2.36 | Three Months | 12-Oct-22 | 11-Jan-23 | CP381 | Completed |
380 | TPQA Services for Five Tribal Schools of Odisha | WAPCOS LIMITED | Dr.Dinakar Pasla | SIF | 25.95 | Two Years | 18-Oct-22 | 17-Oct-24 | CP380 | On-going |
379 | Proof checking of ROB of NH-16, Bhadrak-Balasore road project for SE Railway | BRIJ GOPAL CONSTRUCTION COMPANY PRIVATE LIMITED | Dr. Sumanta Haldar, Associate Propessor | SIF | 2.50 | One Month | 3-Oct-22 | 2-Nov-22 | CP379 | Completed |
378 | Vetting of Electrical and E&M Designs and Drawings of Nawarngpur Project | M/s GVPR ENGINEERS LIMITED | Dr. Srinvas Bhaskar Karanki, Assistant Professor, SES | SES | 7.38 | Nine Months | 13-Oct-22 | 12-May-23 | CP378 | On-going |
377 | The microstructural characterization of advanced high strength steel and suggestions to improve the properties | M/S. JINDAL STAINLESS LIMITED | Dr. Rama Krushna Sabat, Assistant Professor | SMMME | 6.16 | Ten Months | 11-Oct-22 | 10-Aug-23 | CP377 | Completed |
376 | Surface run-off management study for kurmitar iron ore mines of OMC | M/s OMC Ltd | Dr. Arindam Sarkar | SIF | 22.13 | Six Months | 10-Oct-22 | 9-Apr-23 | CP376 | Completed |
375 | Vetting of structural stability of railway bridges | BECQUEREL INDUSTRIES PRIVATE LIMITED | Dr. B Hanumantha Rao, Assistant Professor | SIF | 2.94 | One and Half Month | 29-Sep-22 | 13-Nov-22 | CP375 | On-going |
374 | Vetting the desing and drawing report of gabion wall as a part of WMumbai Coastal Road Project (South) package II | GABION TECHNOLOGIES INDIA PRIVATE LIMITED | Dr. B Hanumantha Rao, Assistant Professor | SIF | 1.03 | One and Half Month | 29-Sep-22 | 13-Nov-22 | CP374 | On-going |
373 | Proof checking of FOB at Ranchi Coast Railway | RAIL VIKAS NIGAM LIMITED | Dr. Dinakar Pasla, Associate Professor | SIF | 1.18 | Two Months | 2-Sep-22 | 1-Nov-22 | CP373 | Completed |
372 | Vetting of Retaining Wall Design, Drawing and Methodology for Repairing of RE wall at km. 349+580 LHS Singhara-Binjhabahal section of NH-6 | M/S MONTECARLO LIMITED | Dr. U C Sahoo | SIF | 2.36 | One Month | 29-Sep-22 | 28-Oct-22 | CP372 | Completed |
371 | Rut Test for BC Grade Mixture | DILIP BUILDCON LIMITED | Dr. Anush K Chandrappa | SIF | 1.18 | One Month | 23-Sep-22 | 22-Oct-22 | CP371 | On-going |
370 | Assesment of soil strength using MASW test at Cuttack | AIMIL LTD | Dr. Sumanta Haldar, Associate Propessor | SIF | 3.00 | One Week | 22-Sep-22 | 29-Sep-22 | CP370 | Completed |
369 | Vetting of desing of embankment for rail track in Ananta CHP Talcher | MAHANADI COALFIELDS LIMITED. | Dr. Sumanta Haldar, Associate Propessor | SIF | 1.18 | Two Weeks | 26-Sep-22 | 10-Oct-22 | CP369 | Completed |
368 | Testing of FlyAsh as per IRC SP 58-2001 to use as an Embankment Fill Material | RKD CONSTRUCTION PVT LTD. | Dr. U C Sahoo | SIF | 1.30 | One Month | 7-Sep-22 | 6-Sep-22 | CP368 | Completed |
367 | Proof checking of Hanger door for AAI, BBSR | TECHNOCRATS SECURITY SYSTEMS PRIVATE LIMITED | Dr. Sumanta Haldar, Associate Propessor | SIF | 1.18 | Two Weeks | 1-Sep-22 | 14-Sep-22 | CP367 | Completed |
366 | Investigation of RE wall Failure at km. 349+580 LHS Singhara-Binjhabahal section of NH-6 | PROJECT DIRECTOR PROJECT IMPLEMENTATION UNIT KEONJHAR | Dr. U C Sahoo | SIF | 2.95 | One Month | 31-Aug-22 | 30-Sep-23 | CP366 | Completed |
365 | Analyzing Co-Occurring Road and Traffic Anomalies using deep learning | Korean Institute of Science and Technology | Dr. Devi Prasad Dogra | SES | 17.79 | One Year | 30-Aug-22 | 29-Aug-23 | CP365 | Completed |
364 | Third Party Construction Quality Testing of Jamujhadi-Basudevpur Dhamar Road | UMSL LTD | Dr. U C Sahoo | SIF | 3.54 | One Month | 29-Aug-22 | 28-Aug-22 | CP364 | Completed |
363 | Proof checking of 3 different height retaining walls at CRWC-Mancheswar | M/s RITES Limited | Dr. Suresh R. Dash | SIF | 1.77 | Three Weeks | 25-Aug-22 | 15-Sep-22 | CP363 | Completed |
362 | Stabilization of Steel Slag usingg Novocrete | NISCO BUILDERS AND DEVELOPERS PRIVATE LIMITED | Dr. U C Sahoo | SIF | 3.98 | Four Months | 17-Aug-22 | 16-Dec-22 | CP362 | Completed |
361 | Scrutiny of Structural design and drawings for Portal at Adityapur and Tata Nagar Railway Station | M/S KEC INTERNATIONAL LTD. | Dr. Suresh R. Dash | SIF | 6.64 | One Month | 10-Aug-22 | 9-Sep-22 | CP361 | Completed |
360 | Mix design for Self Compacting Concrete for SCB Medical College Cuttack | NCC Limited | Dr. Dinakar Pasla, Associate Professor | SIF | 3.04 | Two Months | 22-Jul-22 | 21-Sep-22 | CP360 | Completed |
359 | Water Quality Analysis and Interpretation to check its suitability for construction purpose | NCC Limited | Dr. Manaswini Behera | SIF | 0.40 | Fifteen Days | 18-Jul-22 | 25-Jul-22 | CP359 | Completed |
358 | Design Review for Multi variable Industrial Sensor | HONEYWELL TECHNOLOGY SOLUTIONS LAB PVT. LTD. | Dr. Venugopal Arumuru | SMS | 5.16 | 10 Weeks | 8-Jul-22 | 7-May-23 | CP358 | On-going |
357 | Submission of the analysis of the project specific tariff of Lower Baitarani SHEP | M/s GRIDCO Ltd | Dr. Subhransu Ranjan Samantaray, Associate Professor | SES | 3.32 | One Month | 11-Jul-22 | 10-Aug-22 | CP357 | Completed |
356 | Vetting of Traffic Assessment Report for Shree Ram Construction housing and commercial building project for Environmental Clearance | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED, | Dr. Partha Pratim Dey | SIF | 0.77 | One Week | 8-Jul-22 | 16-Jul-22 | CP356 | Completed |
355 | Mix designs for Koraput district | JMC PROJECTS (INDIA) LIMITED | Dr. Dinakar Pasla, Associate Professor | SIF | 2.60 | Two Months | 9-May-22 | 8-Jul-22 | CP355 | Completed |
354 | Proof checking of Road Mix Design for Hirasar Inteernational Airport, Rajkot | YASHNAND ENGINEERS AND CONTRACTORS PRIVATE LIMITED | Dr. Anush K Chandrappa | SIF | 0.77 | One Month | 18-Jun-22 | 17-Jun-22 | CP354 | Completed |
353 | Vetting of the technical report on slope stabilzation at P4-P5 Noney, Manipur | GABION TECHNOLOGIES INDIA PRIVATE LIMITED | Dr. B Hanumantha Rao, Assistant Professor | SIF | 1.03 | Two Weeks | 7-Jun-22 | 22-Jun-22 | CP353 | On-going |
352 | Soil Core Sample Testing | RE SUSTAINABILITY LIMITED | Dr. B Hanumantha Rao, Assistant Professor | SIF | 1.41 | Eight Weeks | 2-Jun-22 | 28-Jul-22 | CP352 | On-going |
351 | Consultancy services for Structural Peer Review at Ariana Project | M/S KRIDAY REALTY PVT LTD | Dr. Dinakar Pasla, Associate Professor | SIF | 11.80 | Three Months | 3-Jun-22 | 2-Sep-22 | CP351 | Completed |
350 | Conducting detailed design consultancy service for ground improvementt with PVD (prefabricated vertical drains) at high bank locations | INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. B Hanumantha Rao, Assistant Professor | SIF | 5.90 | Two Months | 6-Jun-22 | 5-Aug-22 | CP350 | On-going |
349 | Mix design for Construction of Infrastructure Augmentaion under GE Chilka | SHRI GURMUKHDAS CONTRACTORS PRIVATE LIMITED | Dr. Dinakar Pasla, Associate Professor | SIF | 2.12 | Three Months | 27-Apr-22 | 26-Jul-22 | CP349 | Completed |
348 | Mix Design for structural grade concretes for MGM Plant | GANNON DUNKERLEY & COMPANY LIMITED | Dr. Dinakar Pasla, Associate Professor | SIF | 1.30 | Two Months | 30-Apr-22 | 29-Jun-22 | CP348 | Completed |
347 | Hydrological studies under basement area at TaTa Ariana Bhubaneswar | M/S KRIDAY REALTY PVT LTD | Dr. Arindam Sarkar, Assistant Professor | SIF | 5.24 | Sixteen Months | 30-May-22 | 29-Sep-23 | CP347 | Completed |
346 | Review of design drawings for construction of ground improvement project at red mud stack at Vedanta lanjigarh, Odisha | GARWARE TECHNICAL FIBRES LIMITED | Dr. B Hanumantha Rao, Assistant Professor | SIF | 2.66 | One Month | 18-May-22 | 17-Jun-22 | CP346 | On-going |
345 | Dyke & stack stability study of Part-A and red mud storage plan for plan-B | M/S. UTKAL ALUMINA INTERNATIONAL LTD. | Dr. B Hanumantha Rao, Assistant Professor | SIF | 8.02 | One Year Two Months | 16-May-22 | 15-Jul-23 | CP345 | On-going |
344 | Proof Checking of Design and Drawing of Substructure and Foundation for ROB on NH143 at Champajharan | RKD CONSTRUCTION PVT LTD. | Dr. Suresh Ranjan Dash | SIF | 2.66 | Twenty Days | 7-May-22 | 27-May-22 | CP344 | Completed |
343 | Geotechnical strength of the earthen embankment and Soil Thickness measurement" for Ash Dyke area of Vedanta Limited at Jharsuguda | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED, | Dr. B Hanumantha Rao, Assistant Professor | SIF | 1.62 | One Month | 21-Apr-22 | 20-May-22 | CP343 | On-going |
342 | Proof Checking of Design and Drawing of one ROB and two Non-RDSO standard Minor Bridges for Railway siding at GUA Railway Station, Jharkhand | RITES Ltd (Bhubaneswar) | Dr. Suresh Ranjan Dash | SIF | 6.20 | Two Months | 30-Apr-22 | 29-Jun-22 | CP342 | Completed |
341 | Mix Design for redevelopment and expansion of SCB Medical College, Cuttack under Phase-I | LARSEN & TOUBRO LIMITED | Dr. Dinakar Pasla, Associate Professor | SIF | 8.85 | Three Months | 20-Apr-22 | 24-Jul-22 | CP341 | Completed |
340 | Determination and Analysis of Residual Stress in Aero Engine Compressor Rotor | Indian Air Force | Dr. Manas Mohan Mahapatra | SMS | 17.58 | One Year | 21-Apr-22 | 20-Apr-23 | CP340 | On-going |
339 | Vetting of Traffic Assessment Report for Grand Riviera residential building project for Environmental clearance | GRAND BAZAAR DEVELOPERS LLP | Dr. Rajesh Roshan Dash | SIF | 0.77 | One Week | 2-Apr-22 | 8-Apr-22 | CP339 | Completed |
338 | Execution of Rural Piped water supply project, pertaining to Ranipada Cluster of Banpur Block of Khurda District I/C five year of Operation and Maintenance | UMSL LTD | Dr. Srinvas Bhaskar Karanki, Assistant Professor, SES | SES | 1.48 | Four Months | 3-Apr-22 | 2-Jul-22 | CP338 | On-going |
337 | Mix design and testing of construction materials for SCB Medical College Cuttack | NCC Limited | Dr. Dinakar Pasla, Associate Professor | SIF | 4.30 | Three Months | 7-Apr-22 | 6-Jul-22 | CP337 | Completed |
336 | Technical Support to PMGSY Projects through Laboratory Testing | ARYA CONSTRUCTION C/o Rural Works Department, GoO | Dr. U C Sahoo, Assistant Professor | SIF | 0.30 | One Month | 19-Apr-22 | 18-May-22 | CP336 | On-going |
335 | Proof checking of Design and drawing of Superstructure, Substructure and bearing for the Proposed bridge crossing IOCL Pipelines in connection with proposed Multi-Model Logistic Park/Container Terminal at Paradeep (Odisha) | CONTAINER CORPORATION OF INDIA LIMITED | Dr. Goutam Mondal | SIF | 15.93 | Three Months | 9-Mar-22 | 8-Jun-22 | CP335 | Completed |
334 | Engineering operations philosophy for long term mud management of pond B | M/S. UTKAL ALUMINA INTERNATIONAL LTD. | Dr. B Hanumantha Rao, Assistant Professor | SIF | 4.14 | One Year One Month | 16-Mar-22 | 15-Apr-23 | CP334 | Completed |
333 | Accretion control in kins to enhance campaign life from 60 days to 90 days | SHRI MAHAVIR FERRO ALLOYS (P) LTD | Prof. Brahma Deo, MGM Chair Professor, SMMME | SMMME | 12.98 | Nine Months | 15-Mar-22 | 14-Dec-22 | CP333 | On-going |
332 | Design vetting of the technical report for the proposed gabion wall reinforced by the anchor | M/s Gateway Office Parks Private Limited | Dr B Hanumantha Rao, Assistant Professor | SIF | 1.75 | Two Weeks | 29-Jun-21 | 13-Jul-22 | CP332 | On-going |
331 | Vetting of Traffic Assessment Report for M/s Tirumala Infrastructure and Development (P) Ltd., residential building project at Subudhipur and Shankarpur, for Environmental Clearance | TIRUMALA INFRASTRUCTURE AND DEVELOPMENT PRIVATE LIMITED | Dr. Rajesh Roshan Dash | SIF | 0.77 | One Week | 17-Mar-22 | 25-Mar-22 | CP331 | Completed |
330 | Vetting of Traffic Assessment Report for M/s Shuvam Construction (P) Ltd., building project at Ghatikia for Environmental Clearance | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED, | Dr. Rajesh Roshan Dash | SIF | 0.77 | One Week | 2-Mar-22 | 10-Mar-22 | CP330 | Completed |
329 | Proof checking of Design and Drawings for a Two Lane bridge at Km 432/25-27 over Rly track between Mancheswar-Vanivihar | M/s RAIL VIKAS NIGAM LIMITED | Dr. Dinakar Pasla, Associate Professor | SIF | 2.50 | Three Months | 16-Mar-22 | 16-Jun-22 | CP329 | Completed |
328 | Technical viability of use of Raw Petroleum coke in Manufacturing of ECP/Soderberg Paste | NOC FOUNDATION NEW OPPORTUNITY FOR CHILDRENS | Dr. V Pandu Ranga | SMS | 0.38 | Four Days | 8-Mar-22 | 12-Mar-22 | CP328 | Completed |
327 | Carrying out Proof Checking Overhead Structural Utility Gallery for Tata Steel Kalinganagar | TATA STEEL LIMITED | Dr. Dinakar Pasla, Associate Professor | SIF | 5.90 | Four Months | 18-Feb-22 | 17-Jun-22 | CP327 | Completed |
326 | SS310 Testing by IIT BBSR for SAP HRS TOWER and TFR PIPING | M/s PARADEEP PHOSPHATES LTD. | Dr. Srikant Golapudi, Assistant Professor, SMMME | SIF | 2.35 | Seven Months | 25-Feb-22 | 24-Sep-22 | CP326 | On-going |
325 | Water Quality Analysis and Interpretation to check its suitability for construction purpose | M/s NCC Limited | Dr. Manaswini Behera | SIF | 0.40 | Eighteen Days | 28-Feb-22 | 17-Mar-22 | CP325 | Completed |
324 | Vetting of Traffic Assessment Study for Environmental Clearance of Residential Project of Utkal Builders Limited located at Patia | M/s UTKAL BUILDERS LTD. | Dr. Rajesh Roshan Dash | SIF | 0.77 | Eighteen Days | 8-Feb-22 | 26-Feb-22 | CP324 | Completed |
323 | Vetting of Traffic Assessment Study for Environmental Clearance of Residential Project of Utkal Realtor Pvt Ltd located at Pahal | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED | Dr. Rajesh Roshan Dash | SIF | 0.77 | Eighteen Days | 15-Feb-22 | 5-Mar-22 | CP323 | Completed |
322 | Vetting of the technical report on slope stabilization at slope protection at Noney, Manipur | GABION TECHNOLOGIES INDIA PRIVATE LIMITED | Dr. B Hanumantha Rao, Assistant Professor | SIF | 0.89 | Three Weeks | 8-Feb-22 | 28-Feb-22 | CP322 | On-going |
321 | Proof checking of Design and drawing of foundation (pile and pile cap) for one pier at location of ROB at MCL, Talcher | RITES Ltd (Bhubaneswar) | Dr. Suresh Ranjan Dash | SIF | 1.18 | Two Weeks | 19-Feb-22 | 23-Feb-22 | CP321 | Completed |
320 | Proof checking of flexible pavement design of Duburi-Chandikhol Section of NH-53 | MS INFRA ENGINEERS PRIVATE LIMITED | Dr. Anush K Chandrappa | SIF | 1.76 | One Month | 19-Feb-22 | 18-Mar-22 | CP320 | On-going |
319 | Proof check of bridge no. 4 (ROB) and 5 (Over creek) for IPRCL Bhubaneswar | INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. Devesh Punera, Assistant Professor | SIF | 5.37 | One Month | 17-Feb-22 | 16-Mar-22 | CP319 | Completed |
318 | Manufacturing of Building Blocks | M/S TATA STEEL LIMITED | Dr. Dinakar Pasla, Associate Professor | SIF | 16.99 | Twelve Monhts | 18-Feb-22 | 17-Feb-23 | CP318 | Completed |
317 | Carrying out the vetting of PEB at Hindustan Coca Cola Beverages Pvt Ltd (Building structure design vetting under NBC- for building > 15meters) | AEDBM Consultants Private Limited C/o Hindustan Coca-Cola Beverages Pvt Limited, BBSR | Dr. Dinakar Pasla, Associate Professor | SIF | 2.36 | Three Months | 14-Feb-22 | 13-May-22 | CP317 | Completed |
316 | Vetting of Comprehensive Traffic Density Report for M/s Alishan Realcon Pvt Ltd at Nuahata, Dist Cuttack, Odisha for Environmental Clearance | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED | Dr. Rajesh Roshan Dash | SIF | 0.77 | One Week | 14-Feb-22 | 21-Feb-22 | CP316 | Completed |
315 | Proof checking of 3.0m wide foot over bridge (steel structure) across at Singapur Road station as part of execution of 3rd Railway Line project from TIG-VZM in East Coast Railway | RAIL VIKAS NIGAM LIMITED | Dr. Dinakar Pasla | SIF | 1.18 | Two Months | 31.1.2022 | 4-Feb-22 | CP315 | Completed |
314 | Proof check for major bridge no. 12,13 and 35 for the work "Development for railway infrastructure up to 4 MTPA plant expansion" of Vedanta Limited, Jharsuguda | INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. Devesh Punera | SIF | 6.64 | Two Months | 10.01.2022 | 3-Sep-22 | CP314 | Completed |
313 | Proof Checking of Bridge No.02 (1 X 6 m RCC Slab + 1 X 48.0 m Bow String Girder + 1 X 6 m RCC Slab) | INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. Devesh Punera | SIF | 2.95 | One Month | 10.01.2022 | 2-Sep-22 | CP313 | Completed |
312 | Soil Sample Analysis (Landfill PH-III-B) | RAMKY ENVIRO ENGINEERS LIMITED | Dr. B Hanumantha Rao, Assistant Professor | SIF | 1.41 | One Month | 21-Jan-22 | 20-Feb-22 | CP312 | Completed |
311 | Vetting of Geotechnical Investigation Report Conducted at Kenjaru Village in Mangaluru, Karnataka | M/s SWAYIN & ASSOCIATES | Dr. B Hanumantha Rao, Assistant Professor | SIF | 1.71 | One Month | 18-Jan-22 | 17-Feb-22 | CP311 | Completed |
310 | Proof checking of slopestability and settlement analysis of formation between Ballia Bansdin section of North Eastern Railway | SUTRA CONSULTANCY AND CONSTRUCTIONS | Dr.Sumanta Haldar, Associate Professor | SIF | 1.00 | Two Months | 14-Jan-22 | 13-Mar-22 | CP310 | On-going |
309 | Mix designs for Cuttack Water Supply Project | JMC PROJECTS (INDIA) LIMITED | Dr. Dinakar Pasla, Associate Professor | SIF | 2.73 | Four Months | 19-Jan-22 | 18-May-22 | CP309 | Completed |
308 | Vetting of 2x300 MSV tanks for BPCL at Kondapally, Vijayawada | M/s CREATIVE STUDIO | Dr. Devesh Punera | SIF | 1.69 | Three Weeks | 7-Jan-22 | 31-Jan-22 | CP308 | Completed |
307 | Structural vetting of 5 nos. of bridges of ESL Steel Ltd | M/s PIR Projects and Consultancy Private Limited | Dr. Goutam Mondal | SIF | 4.72 | Three Months | 28-Dec-21 | 27-Mar-22 | CP307 | Completed |
306 | Establishment of Chair Position at IIT Bhubaneswar by OPTCL | M/s ODISHA POWER TRANSMISSION CORPORATION LTD | N.A. | SES | 29.21 | Three Years | 14-Dec-21 | 13-Dec-24 | CP306 | On-going |
305 | Vetting/Consultancy for - "Execution of Rural Piped Water Supply Project pertaining to Ranipada cluster of Banpur Block of Khorda district including five years Operation & Maintenance | M/s UMSL Ltd | Dr. Arindam Sarkar | SIF | 6.75 | Six months | 10-Dec-21 | 9-Jun-22 | CP305 | On-going |
304 | Vetting of Electrical and E&I Designs and Drawings for Bramhagiri & Krushnaprasad block of Puri district of Odisha Project | Voltas Limited | Dr. Srinvas Bhaskar Karanki, Assistant Professor, SES | SES | 4.13 | Nine Months | 7-Dec-21 | 6-Sep-22 | CP304 | Completed |
303 | Vetting of Electrical and E&I Designs and Drawings for Rairakhol block of Sambalpur district of Odisha Project | Voltas Limited | Dr. Srinvas Bhaskar Karanki, Assistant Professor, SES | SES | 4.13 | Nine Months | 7-Dec-21 | 6-Sep-22 | CP303 | Completed |
302 | Concrete Mix Design for the construction of 3km long three lane flyover near joda | M/s RANJIT-CHEVROX (JV) C/o Odisha Bridge & Construction Coporation Limited | Dr. Dinakar Pasla, Associate Professor | SIF | 2.30 | Three Months | 3-Dec-21 | 2-Mar-22 | CP302 | Completed |
301 | Testing of Construction Materials for proposed Rail connectivity of Spur No 3 & 4, Jagannath Washery under Jagannath Area, Talcher | M/s Shanti Construction Sambalpur Pvt Ltd, C/o RITES LTD | Dr. U C Sahoo, Assistant Professor | SIF | 3.72 | Six Weeks | 18-Nov-21 | 29-Dec-21 | CP301 | Completed |
300 | Vetting of Comprehensive Traffic Density Report for M/s Assotech Sun Growth Adobe LLP at Rudrapur, Bhubaneswar, Odisha for Environmental Clearance. | CENTRE FOR ENVOTECH AND MANAGEMENT CONSULTANCY PRIVATE LIMITED, C/o M/s Assotech Sun Growth Adobe LLP at Rudrapur, Bhubaneswar, Odisha | Dr. Rajesh Roshan Dash | SIF | 0.89 | Two Months | 15-Nov-21 | 15-Jan-22 | CP300 | On-going |
299 | Study of failure of beams of Track Hopper & proposal for rectification. | M/s ODISHA POWER GENERATION CORPORATION LIMITED | Dr. Dinakar Pasla, Associate Professor | SIF | 7.00 | Four Months | 11-Oct-21 | 10-Feb-22 | CP299 | Completed |
298 | Monitoring and remedial measures for controlling settlement on the embankment for Kolkata Metro | M/s RAIL VIKAS NIGAM LIMITED | Dr. Sumanta Haldar, Associate Propessor | SIF | 7.08 | Six Months | 30-Oct-21 | 30-Apr-22 | CP298 | Completed |
297 | Proof check for design and detailed engineering and execution of piping, civil & structural jobs related to NG firing facility in GTs at PDR | M/s MCE CONSULTING ENGINEERS PRIVATE LIMITED | Dr. Devesh Punera, Assistant Professor | SIF | 3.50 | Four Months | 4-Oct-21 | 3-Feb-22 | CP297 | On-going |
296 | Proof Checking for Shiv Statue at Jajpur, Odisha | M/s MATU RAM ART CENTRES PRIVATE LIMITED | Dr. Dinakar Pasla | SIF | 2.36 | Two Months | 18-Oct-21 | 18-Dec-21 | CP296 | Completed |
295 | Mix design for construction of Lord Shiva Statue at Jajpur Town | M/s MATU RAM ART CENTRES PRIVATE LIMITED | Dr. Dinakar Pasla | SIF | 1.42 | Two Months | 22-Jul-21 | 22-Sep-21 | CP295 | Completed |
294 | No increase in pollution load certificate for additional products of Portland composite cement (PCC), Masonry cement (MC), Sulfate resisting Portland cement (SRPC). | M/s THE RAMCO CEMENTS LIMITED | Dr. Rama Krushna Sabat | SMMME | 4.72 | One month | 20-Sep-21 | 19-Oct-21 | CP294 | On-going |
293 | Scrutiny of structural design of Sudarshan Vatika | M/s SUDARSHAN ESTCON PRIVATE LIMITED | Dr. Devesh Punera | SIF | 2.66 | One Month | 20-Sep-21 | 19-Oct-21 | CP293 | Completed |
292 | Surface Run-Off Management Study at Gandhamardan Iron Ore Mine Block-A & Block B, M/s OMC Ltd located in Telkoi Tahasil of Keonjhar District Odisha | M/s OMC Ltd | Prof. R K Panda | SIF | 17.70 | One Year | 2-Sep-21 | 1-Sep-22 | CP292 | Completed |
291 | Structural vetting of the Swosti Premium Beach Resorts, a B+G+13 storied resort project situated at Sipasurubuli, Puri. | M/s SWOSTI PREMIUM LIMITED | Dr. Goutam Mondal | SIF | 8.11 | Three Months | 13-Sep-21 | 12-Dec-21 | CP291 | Completed |
290 | Composite roll feasibility study of M/s Deem Rool Technology Pvt Ltd | M/s DEEM ROLL-TECH LIMITED | Dr. Partha Sarathi De | SMMME | 3.82 | Six Months | 17-Aug-21 | 16-Feb-22 | CP290 | On-going |
289 | Consultancy Services for proof checking of the Design Calculations and Working drawings of the bridges and culverts on Non-Government Railway line of The Dhamra Port Company Limited at Dhamra, Odisha | M/s The Dhamra Port Company Ltd | Dr. S R Dash | SIF | 9.96 | Four Months | 2-Sep-21 | 1-Jan-22 | CP289 | Completed |
288 | Carrying out vetting of projects developed by Utkal Developers for Patrapada2, Bhubaneswar | M/s UTKAL BUILDERS LTD | Dr. Dinakar Pasla | SIF | 3.00 | Four Months | 13-Aug-21 | 12-Dec-21 | CP288 | Completed |
287 | Water management at MGM Minerals Limited, Dhenkanal | M/S. MGM MINERALS LIMITED | Dr. Arindam Sarkar | SIF | 26.55 | EIght Months | 12-Aug-21 | 11-Apr-22 | CP287 | On-going |
286 | Construction & upgradation to 2-lane with paved shoulder from Design Km. 67+805(End of 83rd km Tunnel) to Km 80+675 (Start of Kistwar Bypass) of 12.870 Km length on Khellani-Kishtwar-Chattroo section of NH-244 in the Union Territory of Jammu & Kashmir on | M/s A.E.C. INFRASTRUCTURE SERVICES | Dr. Partha Pratim Dey | SIF | 6.20 | Four and Half months | 20-Aug-21 | 4-Jan-22 | CP286 | Completed |
285 | Technical vetting of CAPEX Plan of TPCODL | M/s GRIDCO Ltd | Dr. S R Samantaray | SES | 1.59 | Two Weeks | 17-Aug-21 | 31-Aug-21 | CP285 | Completed |
284 | Product performance study of Dalmia Cements | M/s DALMIA CEMENT (BHARAT) LIMITED | Dr. Dinakar Pasla | SIF | 14.16 | Six Months | 23-Jul-21 | 22-Jan-21 | CP284 | Completed |
283 | Understanding Road Traffic and Pedestrian Anomalies | M/s Korean Institute of Science and Technology (KIST) | Dr. Debi Prosad Dogra | SES | 19.38 | Seven Months | 2-Aug-21 | 1-Feb-22 | CP283 | On-going |
282 | Environmental Audit of secured landfill facility at Paradip Refinery, Paradip, Odisha | M/s Indian Oil Corporation Limited | Dr. Rama Krushna Sabat | SMMME | 2.92 | One Month | 28-Jul-21 | 26-Aug-21 | CP282 | On-going |
281 | No increase in pollution load certificate for constructing 2nd red mud pond | M/s NATIONAL ALUMINIUM CO. LTD | Dr. B Hanumantha Rao | SIF | 1.62 | Nine Weeks | 20-Jul-21 | 22-Sep-21 | CP281 | On-going |
280 | Vetting of Electrical and E&M Designs and Drawings of Puri-Ganjam Project | M/s GVPR ENGINEERS LIMITED | Dr. S B Karanki | SES | 6.20 | Nine Months | 10-Jul-21 | 9-Apr-22 | CP280 | Completed |
279 | Proof checking the Designs and Drawings of Minor Bridges in connection with Jaroll-Jakhpura railway doubling project | M/s RAIL VIKAS NIGAM LIMITED | Dr. S R Dash | SIF | 8.11 | Two Months | 22-Jul-21 | 21-Sep-21 | CP279 | Completed |
278 | Analog Design for Serial Communication | M/s Ceremorphic Inc | Dr. Nijwm Wary | SES | 23.56 | Four Years | 29-Jun-21 | 28-Jun-25 | CP278 | On-going |
277 | Design of non-shrink concrete for Tata Steel Kalinganagar project | M/s TATA STEEL LIMITED | Dr. Dinakar Pasla | SIF | 2.76 | Four Months | 25-Jun-21 | 24-Oct-21 | CP277 | Completed |
276 | Audit on geotechnical investigation, calculations of pile capacity, piling practices, pile test procedures, and suggesting measures for improvement in pile drilling process | M/s INDIAN PORT RAIL & ROPEWAY CORPORATION LIMITED | Dr. B Hanumantha Rao | SIF | 1.90 | FIve Weeks | 31-May-21 | 5-Jul-21 | CP276 | On-going |
275 | Mix designs for M30 grade of concrete using PPC, PSC and SRPC at Chandipur | M/s CMRGS INFRASTRUCTURE PROJECTS LTD. | Dr. Dinakar Pasla | SIF | 1.53 | Two Months | 3-Jun-21 | 2-Aug-21 | CP275 | Completed |
274 | Proof checking of the design of Railway Foot Over Bridge (Steel Structure) at AMB station yard | M/s RAIL VIKAS NIGAM LIMITED | Dr. Dinakar Pasla | SIF | 1.18 | Two months | 25-May-21 | 24-Jul-21 | CP274 | Completed |
273 | Development of Concrete Mix Designs for IIM Sambalpur | M/s DEE VEE PROJECTS LIMITED | Dr. Dinakar Pasla | SIF | 3.68 | Four Months | 1-Jun-21 | 30-Sep-21 | CP273 | Completed |
272 | Vetting of new South-west red mud pond and PWL (Process Water Lake) designs | M/S VEDANTA LIMITED ALUMINIUM & POWER | Dr. B Hanumantha Rao | SIF | 27.86 | SIx Months | 27-May-21 | 26-Nov-21 | CP272 | On-going |
271 | Mix design for Construction of Substructure and Superstructure at Chandipur | M/s LIRA CONSTRUCTIONS PRIVATE LIMITED | Dr. Dinakar Pasla | SIF | 1.18 | Two Months | 3-May-21 | 2-Jul-21 | CP271 | Completed |
270 | Proof checking of foot over bridge and overhead piping crossing railway track for Tata Steel | M/s Tata Steel Limited | Dr. Dinakar Pasla | SIF | 8.56 | SIx Months | 20-May-21 | 19-Nov-21 | CP270 | Completed |
269 | Testing of TMT Rebar | M/s Rungta Mines Limited C/o R&D & Q.P (R&B), Govt. of Odisha | Dr. Soobhankar Pati | SMMME | 4.78 | 15 days | 30-Mar-21 | 14-Apr-21 | CP269 | Completed |
268 | Soil core lab testing | M/s Ramky Enviro Engineers Limited | Dr. B Hanumantha Rao | SIF | 1.41 | One Month | 5-Mar-21 | 4-Apr-21 | CP268 | Completed |
267 | Environmental Audit of CHWTSDF | M/s Ramky Enviro Engineers Limited | Dr. B Hanumantha Rao | SIF | 5.06 | Three Months | 5-Mar-21 | 4-Jun-21 | CP267 | Completed |
266 | Development of Hydrophobic Concrete for Seabird Project | M/s Master Builders Solutions India Private Limited | Dr. Dinakar Pasla | SIF | 5.37 | Four Months | 30-Mar-21 | 29-Jul-21 | CP266 | Completed |
265 | Vetting of GTI rock fall protection netting specifications "D-WR" | GABION TECHNOLOGIES INDIA PRIVATE LIMITED | Dr. B Hanumantha Rao | SIF | 1.30 | 49 days | 8-Mar-21 | 25-Apr-21 | CP265 | On-going |
264 | Measurement of factor of safety for tailings dams of RMP & ash pond at Vedanta Limited | VEDANTA LIMITED ALUMINIUM & POWER | Dr. B Hanumantha Rao | SIF | 6.14 | 39 days | 17-Mar-21 | 24-Apr-21 | CP264 | On-going |
263 | Vetting of box culvert design of Jeypore airport under RCS-UDAN (Long Term) | DIRECTORATE OF AVIATION BHUBANESWAR C/o M/s Nirman Soudha | Dr. Goutam Mondal | SIF | 2.21 | Three Months | 26-Mar-21 | 25-Jun-21 | CP263 | Completed |
262 | Proof checking of the structural design & drawing of PEB Hangar at Biju Patnaik international Airport, Bhubaneswar | M/s Yazdani International Pvt.Ltd/ C/o Capt Zaheed Parvez | Dr. Goutam Mondal | SIF | 5.61 | Three Months | 30-Mar-21 | 29-Jun-21 | CP262 | Completed |
261 | Structural Scrutiny of Railway Buildings | M/s PIR Projects and Consultancy Private Limited | Dr. Goutam Mondal | SIF | 1.48 | Two Months | 17-Mar-21 | 16-May-21 | CP261 | Completed |
260 | Consultancy for corrective action for cracks developed during launching of pre-cast rcc box segment (span 2 x 6.0 x 6.0 m) | M/s RITES Limited | Dr. S R Dash | SIF | 1.99 | 21 days | 26-Mar-21 | 15-Apr-21 | CP260 | Completed |
259 | Environmental Audit of secured landfill in smelter plant NALCO at Angul | NALCO | Dr. R R Dash | SIF | 3.45 | Two Months | 20-Mar-21 | 19-May-21 | CP259 | Completed |
258 | Dike & Stability study of red mud storage pond-A | M/S. UTKAL ALUMINA INTERNATIONAL LTD | Dr. B Hanumantha Rao | SIF | 9.56 | One Month | 26-Feb-21 | 25-Mar-21 | CP258 | On-going |
257 | Design of CGBM using Provence 907, a ready mix grout | M/s Avijeet Agencies Pvt.Ltd | Dr. U C Sahoo | SIF | 2.36 | Three Months | 16-Mar-21 | 15-Jun-21 | CP257 | Completed |
256 | Vetting of soil investigation report for the work: Soil Investigation For Provision of Deficient Integrated Security Watch Towers Under GE (P) Ezhimala at INA Ezhimala. | M/s IDAX Consultanting and Research Pvt. Ltd | Dr. Sumanta Haldar, Associate Propessor | SIF | 0.59 | 15 Days | 5-Mar-21 | 20-Mar-21 | CP256 | Completed |
255 | Rehabilitation and Up-gradation of Road from Km 0.000 to Km 16.290 (Lenggth- 16.290 km) of Manu-Lalcherra section of NH 44A to two lane with Paved shoulder in the state of Triupra on EPC basis (pkg-1)- safety consultant service reg. | M/s SSK Infrastructures | Dr Partha Pratim Dey | SIF | 2.66 | Eighteen Months | 9-Mar-21 | 8-Sep-22 | CP255 | Completed |
254 | Proof check of Major Bridge No. 8b of PEQCTPL siding at Paradeep | M/s Indian Port Rail & Ropeway Corporation Ltd. (IPRCL) Bhubaneswar | Dr Devesh Punera | SIF | 2.43 | One Month | 23-Feb-21 | 22-Mar-21 | CP254 | Completed |
253 | Carrying out Mix-designs of concrete for the Widening & Strengthening of Sankara Bypass Road | M/s Altima Infrastructure Private Limited, C/O NBCC (India) Limited | Dr. Dinakar Pasla | SIF | 1.84 | Two Months | 10-Feb-21 | 9-Apr-21 | CP253 | Completed |
252 | Proof check and scrutiny of designs and drawings of substructure for 3 nos of major bridges in connection with NTPC-LARA project | M/s RITES Limited | Dr. Suresh R Dash | SIF | 11.34 | Two Months | 5-Feb-21 | 4-Apr-21 | CP252 | On-going |
251 | Carrying out vetting of projects developed by Utkal Developers Bhubaneswar for Patrapada | M/s Utkal Builders | Dr. Dinakar Pasla | SIF | 2.78 | Four Months | 19-Nov-20 | 18-Mar-21 | CP251 | Completed |
250 | Testing of spray concrete panels with PP fibers | M/s Master Builders Solutions India Private Limited, C/0 M/s BASF India Ltd | Dr. Dinakar Pasla | SIF | 3.59 | Three Months | 8-Jan-21 | 7-Apr-21 | CP250 | Completed |
249 | Stability test of ash dikes | M/s Jindal India Thermal Power Limited | Dr. B Hanumantha Rao | SIF | 6.49 | One Month | 14-Jan-21 | 13-Feb-21 | CP249 | On-going |
248 | Proof checking of design and drawing of six Nos of minor bridges (Non-RDSO standard RCC Box) at Brajrajnagar, Jharsuguda | M/s RITES Limited | Dr. Suresh R Dash | SIF | 7.18 | Two Months | 25-Jan-21 | 24-Mar-21 | CP248 | Completed |
247 | Surface Run-Off Management studies at Daitari Iron Ore Mine, South Kaliapani Chromite Mine and Sukrangi Chromite Mines, M/s OMC Ltd | The Odisha Mining Corporation Ltd | Prof. R K Panda | SIF | 25.08 | One Year | 29-Jan-21 | 28-Jan-22 | CP247 | Completed |
246 | Suggesting measures for road failure at a hill section of NH-57 | M/s SCIW-YFC Joint Venture | Dr. Umesh Chandra Sahoo | SIF | 3.54 | Two Months | 30-Jan-21 | 30-Mar-21 | CP246 | Completed |
245 | Vetting of design note on slope stability | M/s Sai Gr Impex Pvt.Ltd | Dr. B Hanumantha Rao | SIF | 1.01 | One Month | 17-Dec-20 | 16-Jan-21 | CP245 | On-going |
244 | Vetting of Design of Wastewater Treatment plant equipment units for STPs, ETPs, and SRTs | M/s SJ Environmental Solutions | Dr. Rajesh roshan Dash | SIF | 1.24 | One Month | 18-Jan-21 | 17-Feb-21 | CP244 | Completed |
243 | Proof checking of Design and drawing of substructure for bridge in connection with Angul-Sukinda new BG Rail link Project | M/s Rail Vikas Nigam Limited | Dr. Suresh R Dash | SIF | 9.88 | Two Months | 5-Jan-21 | 4-Mar-21 | CP243 | Completed |
242 | Regional and Sub-regional Analyses of Macroeconomic Policy Strategies for Growth and Equality in Southern Africa | United Nations University World Institute for Development Economics Research | Dr. Dukhabandu Sahoo | SHSSM | 7.29 | 230 Days | 15-Apr-20 | 31-Dec-20 | CP242 | Completed |
241 | Impact Assessment of WHO's framework convention on Tobacco control (FCTC) in India-A call to action report 2021 | M/s AF Development Care (AFDC) | Dr. Dukhabandu Sahoo | SHSSM | 12.64 | 4 Months | 12-Jan-21 | 11-May-21 | CP241 | Cancelled |
240 | Design and formulation of coating using molecular modelling and simulation | M/s Tata Steel Ltd | Prof. S K Nayak | SBS | 26.90 | 1 Year | 8-Jan-21 | 7-Jan-22 | CP240 | On-going |
239 | Development of static model for Tata steel BOF | Tata Steel Ltd | Prof. Brahma Deo | SMMME | 31.86 | 1 Year | 18-Dec-20 | 17-Dec-21 | CP239 | Completed |
238 | Product development and technical support for cold mix Asphalt Application in Eastern India | Bitchem Asphalt Technologies Ltd | Dr. U C sahoo | SIF | 35.40 | 3 years | 24-Dec-20 | 23-Dec-23 | CP238 | On-going |
237 | Assessment study for issue of “no increase in pollution load” certificate to Paradip Refinery cum Petrochemical complex for processing crude oil above name plate capacity of 15 MMTPA = 10% max | Indian Oil Corporation Ltd | Dr. Rama Krushna Sabat | SMMME | 4.22 | 3 months | 20-Nov-20 | 19-Jan-21 | CP237 | Completed |
236 | Vetting of traffic density study traffic density study for environmental clearance for TATA-Bhusan township at Angul | Centre for Envotech and management | Dr. R R Dash | SIF | 1.77 | 3 months | 19-Nov-20 | 18-Feb-21 | CP236 | Completed |
235 | Design and drawing of building of SSRM and HRO, RMS 'N' Division, Cuttack, Odisha | Postal Civil Division | Dr. Sumanta Halder | SIF | 5.00 | 1 month | 30-Sep-20 | 30-Oct-20 | CP235 | Completed |
234 | Carrying out vetting of projects developed by Utkal developers Bhubaneswar | Utkal Builders Pvt. Ltd | Dr. Dinakar Pasla | SIF | 2.78 | 4 months | 6-Oct-20 | 5-Feb-21 | CP234 | Completed |
233 | Vetting of Traffic Density Study for Environmental Clearance for Housing project at Pahala, Bhubaneswar | Centre for Envotech and management | Dr. P P Dey | SIF | 0.83 | 3 months | 13-Oct-20 | 12-Jan-21 | CP233 | Completed |
232 | Study the cause of defect on the wing walls of Br. 5 over Angul-Balaram Section of MCRL corridor and suggestion on remedial measures for the structure | IRCON International Ltd | Dr. S R Dash | SIF | 4.13 | 3 months | 29-Sep-20 | 28-Dec-20 | CP232 | Completed |
231 | Evaluation of PPC, PSC and Composite cements of Dalmia Cements | Dalmia Cements Bharat | Dr. Dinakar Pasla | SIF | 2.10 | 6 months | 10-Aug-20 | 9-Feb-21 | CP231 | Completed |
230 | Carrying out the third party quality assurance consultancy (TPQAC) for the construction and development of Kendriya Vidyalaya Schoolat Jagatsinghpur, Odisha | National Projects Construction Cooperation Ltd | Dr. Dinakar Pasla | SIF | 7.57 | 18 months | 16-Sep-20 | 15-Mar-22 | CP230 | Completed |
229 | Proof checking of design and drawing of substructure and foundation of 5 major bridge at Brajrajnagar, Jharsuguda | RITES Ltd | Dr. S R Dash | SIF | 21.54 | 1 year | 7-Sep-20 | 6-Sep-21 | CP229 | Completed |
228 | Residual Stress Measurement on Rotor Surface at various Locations (Base Metal & Weld) & Modelling of Rotor Weldment-For AUSC Projects | Bharat Heavy Electricals Limited | Dr. M M Mahapatra | SMS | 9.20 | 3 months | 24-Aug-20 | 23-Nov-20 | CP228 | Completed |
227 | Testing of TMT Bars as per IS:1786:2008 | Office of Chief Engineer, Research Development & quality Promotion, Odisha | Dr. Soobhankar Pati | SMMME | 1.78 | 2 Weeks | 11-Aug-20 | 25-Aug-20 | CP227 | Completed |
226 | Carrying out concrete mix designs for new greenfield airport at Hirasaar, Rajkot (Gujarat) | Dillip Buildcon Ltd | Dr. Dinakar Pasla | SIF | 12.04 | 6 months | 12-Aug-20 | 10-Feb-21 | CP226 | Completed |
225 | Proof check and scrutiny of design and drawings of bridge substructure and foundation (Br.3 and Br.79) in connection with NTPC-LARA project | RITES Ltd | Dr. S R Dash | SIF | 6.93 | 4 months | 5-Aug-20 | 5-Dec-20 | CP225 | Completed |
224 | Carrying out concrete mix design for AIIMS Bhubaneswar second phase of construction | CPWD | Dr. Dinakar Pasla | SIF | 1.00 | 2 months | 28-Jul-20 | 28-Sep-20 | CP224 | Completed |
223 | Proof checking of design and drawing of substructure for Bridge No. 180(ROB) | Rail Vikas Nigam Limited | Dr. S R Dash | SIF | 2.14 | 1 month | 24-Jul-20 | 23-Aug-20 | CP223 | Completed |
222 | Proof checking of detailed design and drawing for construction of New Greenfield Airport at Rajkot, Gujarat | Dillip Buildcon Ltd | Dr. Anush K C | SIF | 23.60 | 1 year | 18-Jul-20 | 17-Jul-21 | CP222 | Completed |
221 | Preparation of catchment area treatment plan for the Dubuna Sakradihi iron and manganese ore mines of OMC Ltd. | OMC | Prof. R K Panda | SIF | 22.13 | 3 months | 2-Jul-20 | 2-Oct-20 | CP221 | On-going |
220 | Anomaly Detection in Videos | KIST | Dr. D P Dogra | SES | 23.79 | 1 year | 26-Jun-20 | 24-Feb-21 | CP220 | Completed |
219 | Soil core lab testing | Ramky | Dr. B hanumatha Rao | SIF | 2.87 | 1 month | 23-Jun-20 | 22-Jul-20 | CP219 | On-going |
218 | Mathematical modelling for parameter estimation and vibration analysis | ITR, DRDO | Dr. S R Kannan | SMS | 8.30 | 6 months | 16-Jun-20 | 15-Dec-20 | CP218 | Completed |
217 | ov | PIR Projects and Consultancy Private Limited | Dr. Goutam Mondal | SIF | 3.54 | 2 months | 24-Jun-20 | 24-Aug-20 | CP217 | Completed |
216 | Design and development of gaseous Oxygen heat exchanger for semi-cryogenic stage | Liquid Propulsion Systems Centre | Dr. Prasenjit Rath | SMS | 5.00 | 11 months | 3-May-20 | 29-Mar-21 | CP216 | On-going |
215 | Structural vetting of residential towers as per the BDA, Odisha | Mani Tirumala | Dr. Devesh Punera | SIF | 5.00 | 1 month | 5-Jun-20 | 4-Jul-20 | CP215 | Completed |
214 | Technological interventions to reduce humananimal conflict | State wildlife | Prof. N C Sahoo Dr. S N Panigrahi Dr. Vijaykrishna kari Dr. Mithipati sivabhaskar | IIT | 50.00 | 1 year | 3-Jun-20 | 30-Sep-23 | CP214 | On-going |
213 | Proof checking of the design and drawing of ROBs for KMC-RKD | RKD Construction (P) Ltd. | Dr. S R Dash | SIF | 10.84 | 2 months | 19-May-20 | 19-Jul-20 | CP213 | Completed |
212 | Proof checking of design and drawing of one of the revised substructure (Pier-P1) of Br. 172 in connection with Angul-Sukinda New B.G Rail link Project | Rail Vikas Nigam Limited | Dr. S R Dash | SIF | 1.53 | 3 weeks | 18-May-20 | 8-Jun-20 | CP212 | On-going |
211 | Vetting of 3.0m height retaining wall sheet at VSS airport, Jharsuguda | Airport Authority of India PR Construction | Dr. Dinakar Pasla | SIF | 1.00 | 3 months | 15-May-20 | 15-Aug-20 | CP211 | Completed |
210 | Database for Principal Technical Agency & State Technical Agency for states of Jharkhand and Odisha | NRRDA | Dr. U C Sahoo | SIF | 82.58 | 1-Apr-20 | 31-Mar-24 | CP210 | On-going | |
209 | Testing of samples for integrated Infrastructure Complex at Dhamnagar, Bhadrak | Bridge and Roof Co, (India) Ltd. | Dr. Dinakar Pasla | SIF | 1.04 | 2 months | 12-Mar-20 | 12-May-20 | CP209 | Completed |
208 | Vetting of construction of civil works for installation of ILS at VSS airport Jharsuguda | Airport Authority of India PR Construction | Dr. Dinakar Pasla | SIF | 1.00 | 3 months | 2-Jan-20 | 2-Apr-20 | CP208 | Completed |
207 | Proof checking of design and drawing of road under bridge (RUB) at MCL, Talcher (span 2x6.0x6.0m RCC PRECAST SEGMENTAL BOX) | RITES Ltd | Dr. S R Dash | SIF | 2.02 | 1 month | 21-Mar-20 | 20-Apr-20 | CP207 | Completed |
206 | Vetting of new South-west red mud pond and PWL (process Water Lake) designs | Vedanta Ltd | Dr. B hanumatha Rao | SIF | 27.86 | 6 months | 25-Feb-20 | CP206 | Cancelled | |
205 | Study of ground water table and surface water discharge at Tata Steel Kalinganagar | Tata Steel Ltd | Dr. Arindam Sarkar | SIF | 14.75 | 3 months | 5-Feb-20 | 5-May-20 | CP205 | Completed |
204 | Proof check and scrutiny of design and drawings of 1 major bridge substructure and foundation in connection to NTPC-LARA project | RITES Ltd | Dr. S R Dash | SIF | 5.75 | 6 weeks | 27-Jan-20 | 9-Mar-20 | CP204 | Completed |
203 | “Design of Cell filled concrete pavements for rural roads carrying heavy traffic | M/s Kohinoor Plastech, Kolkata | Dr. Anush K C | SIF | 3.98 | 4 months | 8-Jan-20 | 8-May-20 | CP203 | On-going |
202 | Checking of the stability of foundation and superstructure of pipe conveyor for MCL | M/s L&T Ltd. | Dr. Sumanta Halder | SIF | 3.98 | 2 months | 4-Jan-20 | 4-Mar-20 | CP202 | Completed |
201 | Site study at Barang for Construction of Cancer Hospital | Alamelu Charitable Foundation (Tata Trusts) | Dr. Dinakar Pasla | SIF | 1.48 | 1 months | 3-Jan-20 | 2-Feb-20 | CP201 | Completed |
200 | Mix Design for NTPC-BHEL Project at BARH | RDC Concrete India Ltd | Dr. Dinakar Pasla | SIF | 1.53 | 3 months | 8-Jan-20 | 8-Apr-20 | CP200 | Completed |
199 | Vetting of Traffic Density Study for Environmental Clearance for Multiplex Building at Bhubaneswar | M/s CEMC Pvt. Ltd | Dr. R R Dash | SIF | 0.89 | 15 days | 30-Dec-19 | 14-Jan-20 | CP199 | Completed |
198 | Verification of Hydraulic & structural design and drawings of RWSS Mega Water Project of Puri District | M/s Voltas Limited | Dr. Puspendu Bhunia | SIF | 29.50 | 6 months | 27-Dec-19 | 26-Jun-20 | CP198 | Completed |
197 | Technical support for rehabilitation of defunct NH-5, Balugaon from 0/0 km to 8/0 km | Chief Engineer (DPI & Roads) Odisha, Govt. of Odisha | Dr. U C Sahoo | SIF | 3.98 | 3 months | 6-Dec-19 | 6-Mar-20 | CP197 | Completed |
196 | Structural vetting of bridges and retaining walls of 2x25MW Maithan Right Bank Thermal Power Project for M/s L&T Ltd | L&T Ltd | Dr. S R Dash | SIF | 29.50 | 3 months | 4-Dec-19 | 4-Mar-20 | CP196 | Completed |
195 | Design verification of Boudh WSP | Larsen & Toubro (L&T) Construction | Dr. Dinakar Pasla | SIF | 5.90 | 4 months | 3-Dec-19 | 3-Apr-20 | CP195 | Completed |
194 | Stability analysis and method of improving the bearing capacity from KM 56.00 to KM 57.10 - Package 2A (Construction of road bed, station buildings, passenger amenities, minor bridges, general electrical works in connection with new BG rail line from Kendrapara (Incl) KM 42.040 to Dumuku Km 57.000 on Khurdha road division of East Coast Railway in the State of Odisha, India | Rail Vikas Nigam Limited | Dr. B hanumatha Rao | SIF | 4.06 | 2 month | 1-Dec-19 | 1-Feb-20 | CP194 | Completed |
193 | Technical Scrutiny of structural drawing and design calculations of 3x300 MSV and 1x600 MSV tank | Creative Studio | Dr. Devesh Punera | SIF | 1.77 | 1 month | 18-Nov-19 | 18-Dec-19 | CP193 | Completed |
192 | Verification of basic and detailed engineering design of RWSS mega water project of Rairakhol | Voltas Limited | Dr. Arindam Sarkar | SIF | 29.50 | 6 months | 19-Nov-19 | 19-May-20 | CP192 | Completed |
191 | Stability study in tailings dams and scrutiny of dry stacking procedure of red mud | Vedanta Limited | Dr. B Hanumatha Rao | SIF | 16.92 | 6 months | 24-Oct-19 | 23-Apr-20 | CP191 | Completed |
190 | Mix Design for married Accommodation at Chandipur | Military Engineer Services through M/s Komal Buildcon Pvt. Ltd, Jaipur, Rajasthan | Dr. Dinakar Pasla | SIF | 1.15 | 2 months | 1-Nov-19 | 1-Jan-20 | CP190 | Completed |
189 | Testing of Bituminous core samples of Paga-Gopinathpur-Kuanpal Road | Executive Engineer, QC(R&B) Div. Govt. of Odisha | Dr. U C Sahoo | SIF | 1.19 | 15 days | 30-Oct-19 | 14-Nov-19 | CP189 | Completed |
188 | Structural vetting of 17 bridges for M/s Adani Infra (India) Ltd. At Hansdiha Godda Section under Eastern Railway | PIR Projects and Consultancy Private Limited | Dr. Goutam Mondal | SIF | 23.60 | 6 months | 1-Oct-19 | 31-Mar-20 | CP188 | Completed |
187 | Proof checking of design/drawings of bearings with reference to the grade separator structure at Khandagiri Chowk (Km. 412) on NH-5 (New NH-16), Bhubaneswar | RKD Construction Pvt. Ltd | Dr. S R Dash | SIF | 3.54 | 3 months | 26-Sep-19 | 26-Dec-19 | CP187 | Completed |
186 | Coriolis flowmeter study | Honeywell Technology Solutions Lab Pvt. Ltd | Dr. Venugopal Arumuru | SMS | 13.00 | 1 Year | 18-Sep-19 | 16-Sep-20 | CP186 | Completed |
185 | Design and development of Flow measurement Solution | Honeywell Technology Solutions Lab Pvt. Ltd | Dr. Venugopal Arumuru | SMS | 21.50 | 1 Year | 18-Sep-19 | 16-Sep-20 | CP185 | Completed |
184 | Checking Structural strength of pier of east coast railway constructed over luna river | Rail Vikas Nigam | Dr. Dinakar Pasla | SIF | 1.06 | 1 month | 20-Sep-19 | 20-Oct-19 | CP184 | Completed |
183 | Design of M25 Grade RCC for Structural Elements | M/s Airports Authority of India, Jharsuguda | Dr. Dinakar Pasla | SIF | 1.01 | 2 months | 31-Aug-19 | 31-Oct-19 | CP183 | Completed |
182 | 2nd phase monitoring settlements and effectiveness of the PVD-Package 2B - Construction of road bed, station buildings, passenger amenities, minor bridges, general electrical works in connection with new BG rail line from Dumuku KM 57.000 to Nuagaon KM 68.300 on Khurdha roda division of East Coast Railway in the state of Odisha, India | M/s RVNL, Bhubaneswar | Dr. B hanumatha Rao | SIF | 2.00 | 15 days | 31-Aug-19 | 15-Sep-19 | CP182 | Completed |
181 | Product quality improvement program at Deem Roll Tech. Ltd | M/s Deem Roll Tech. Ltd., Ahmedabad | Dr. P P Dey | SMMME | 0.61 | 2 months | 8-Aug-19 | 8-Oct-19 | CP181 | Completed |
180 | Re-identification guided video synopsis | Korea Institute of Science and Technology (KIST) | Dr. Debi Prosad Dogra | SES | 18.34 | 9 months | 9-Aug-19 | 9-May-20 | CP180 | Completed |
179 | Request to assess the structural integrity of sports climbing wall | Dept. of Sports & Youth Services | Dr. Dinakar Pasla | SIF | 5.61 | 3 months | 9-Aug-19 | 9-Nov-19 | CP179 | Completed |
178 | Testing suitability of dredged sand for use in Road embankment & subgrade | Executive Engineer, R&D Division, Bhadrak | Dr. U C sahoo | SIF | 2.39 | 2 months | 17-Jul-19 | 17-Sep-19 | CP178 | Completed |
177 | Structural vetting of proposed bridge for Private Railway siding near Barbil Station of Chakradharpur division in South Eastern Railway to serve M/s Rungta Mines Ltd | M/s PIR Projects and Consultancy Private Limited | Dr. Goutam Mondal | SIF | 2.95 | 6 months | 14-Jun-19 | 13-Dec-19 | CP177 | Completed |
176 | Core sample analysis of composite clay lining of secured engineering landfill for disposal of hazardous waste | M/s RAMKY Enviro Engineers Ltd | Dr. B hanumatha Rao | SIF | 1.26 | 15 days | 21-May-19 | 5-Jun-19 | CP176 | Completed |
175 | Engineering operation philosophy for long term mud management | Utkal Alumina International Limited | Dr. B hanumatha Rao | SIF | 21.48 | 9 months | 16-Apr-19 | 16-Jan-20 | CP175 | Completed |
174 | Checking of bearing capacity of pile for LPG bottling plant IOCL | M/s Kosan SFPL projects (P) Ltd. | Dr. Dinakar Pasla | SIF | 1.50 | 1 month | 20-May-19 | 19-Jun-19 | CP174 | Completed |
173 | Structural vetting of proposed bridge for Private Railway Siding at Mahalimarup Station to serve M/s Shree Cement Ltd, and at Lathikata of Chakradharpur division in South Eastern Railway to serve M/s Orissa Industries Ltd | M/s Picasona Rail Engineers & Project Private Limited | Dr. Goutam Mondal | SIF | 5.16 | 2 months | 10-May-19 | 10-Jul-19 | CP173 | Completed |
172 | Technical scrutiny of Drawing and Design of Thrust Bed for Box Pushing Section Below Railway Track | M/s Tata Steel Limited | Dr. Devesh Punera | SIF | 2.21 | 1 month | 29-Apr-19 | 29-May-19 | CP172 | Completed |
171 | Vetting of structure design/drawing for the project of KV for 6 locations at Jharkhand & Odisha State | M/s CP & DS Associates, Ghaziabad | Dr. Sumanta Halder | SIF | 5.07 | 10 months | 11-Mar-19 | 5-Jan-20 | CP171 | Completed |
170 | Residual stress measurement by Deep-hole drilling technique | NMRL, DRDO | Dr. M M Mahapatra | SMS | 39.80 | 1 year | 20-Mar-19 | 31-Mar-21 | CP170 | On-going |
169 | Development of FEM model for Design Improvement of multi layered Baffle | NPOL, DRDO | Dr. S N Panigrahi | SMS | 18.75 | 1 year | 12-Mar-19 | 10-Mar-20 | CP169 | Completed |
168 | Testing of ferroalloy slag granules | M/s Nava Bharat Ventures Limited | Dr. B hanumatha Rao | SIF | 1.27 | 20 days | 22-Mar-19 | 19-Jul-19 | CP168 | Completed |
167 | Mix design for M30 and M35 grade of Concretes | M/s Ultratech Cement Ltd | Dr. Dinakar Pasla | SIF | 1.03 | 45 days | 19-Mar-19 | 31-Aug-19 | CP167 | Completed |
166 | Construction of new road at the missing link portion of NH81 along the approved alighment between Harischandrapur & Eastern approach of Kalindri - Bridge from Km 46.550 to Km 59.697 in the district of Malda West Bengal on EPC m | M/s Dynamic Projects Pvt. Ltd. | Dr. P P Dey | SIF | 1.18 | 1 year | 4-Feb-19 | 3-Feb-20 | CP166 | Completed |
165 | Analysis of side slope failure and base failure and suggestion of corrective measures in connection with Angul-Sukinda New Railway Line project | Rail Vikas Nigam Limited | Dr. S R Dash | SIF | 11.80 | 3 months | 14-Mar-19 | 14-Jun-19 | CP165 | Completed |
164 | Proof checking of design and drawing of superstructure and substructure of a ROB at Tata Steel Plant, Kalinganagar (Span 2X36m Composite Girder) | RITES Ltd | Dr. S R Dash | SIF | 6.64 | 2 months | 15-Mar-19 | 15-May-19 | CP164 | Completed |
163 | Safety Analysis of Steel Pipeline Crossing Railroad between Surat and Vadodara | M/s Dedicated Freight Corridor Corporation of India Ltd | Dr. S R Dash | SIF | 4.13 | 1 month | 6-Mar-19 | 5-Apr-19 | CP163 | Completed |
162 | Technical vetting of foundations F1 type, F2 type and F3 type and pedestals of ETP shed at IOCL Guwahati | M/s Minakshi Sarkar Engineering and Valuers | Dr. Goutam Mondal | SIF | 1.37 | 2 months | 1-Mar-19 | 1-May-19 | CP162 | Completed |
161 | Proof checking of detailed design / drawing and calculation of foot over bridge for TSK | M/s Tata Steel Limited, Kalinganagar | Dr. Dinakar Pasla | SIF | 11.80 | 3 months | 28-Jan-19 | 28-Apr-19 | CP161 | Completed |
160 | Process related improvements at PPL | M/s Paradeep Phosphates Ltd | Prof. Brahma Deo | SMMME | 35.71 | 15 months | 21-Jan-19 | 20-Apr-20 | CP160 | Completed |
159 | Upgradation of NH-512 with a minimum of 2-Lane with paved shoulder configuration starting from Ch 82.4 km to 99.5 km and minimum of 4-Lane configuration from Ch 104.2 km to Ch 106.607 km on EPC mode in State of West Bengal under Annual Plan 2017-18 | M/s Millenium Road Construction Pvt. Ltd | Dr. P P Dey | SIF | 1.18 | 1 year | 15-Jan-19 | 14-Jan-20 | CP159 | Completed |
158 | Concrete Mix Design for MMLP Paradip | M/s Ircon Infrastructure Services Ltd | Dr. Dinakar Pasla | SIF | 4.30 | 2 months | 20-Dec-18 | 20-Feb-19 | CP158 | Completed |
157 | Construction of widening to 2-lane with paved shoulder including geometric improvement Ch.318.650 km to 339.940 km (Length 21.949 km) on Churaibari to Agartala section of NH8 (Old NH44) in the state of Tripura on EPC mode (Length 21.9 km) | M/s Ram Kripal Singh Construction Pvt. Ltd | Dr. P P Dey | SIF | 1.77 | 1.5 year | 24-Dec-18 | 23-Jun-20 | CP157 | Completed |
156 | Implementation of Advanced Machine Learning Algorithms for Cluster Expansion | M/s Indo Korea Science and Technology Center, Bangalore | Dr. Debi Prosad Dogra | SES | 28.83 | 4 years | 24-Dec-18 | 23-Dec-21 | CP156 | Completed |
155 | Technical Scrutiny of Launching Scheme of 2 Nos. Steel girder of RUB No. 46 at NH-49 at NH-49 between Belpahar and Brajrajnagar for OPGC Limited | M/s Larsen & Tubro Ltd | Dr. Goutam Mondal | SIF | 4.43 | 2 months | 6-Dec-18 | 6-Feb-19 | CP155 | Completed |
154 | Stability Analysis of Core formation with sand and local earth for new BG Rail line from Nuagaon to Paradeep | M/s Rail Vikas Nigam Limited, Bhubaneswar | Dr. Sumanta Halder | SIF | 1.65 | 1 month | 12-Dec-18 | 11-Jan-19 | CP154 | Completed |
153 | A Model Based Decision Support & Control System for Accretion Control to increase the sponge iron production to the target annual capacity of 4,25,000 Mt through a R&D Project | M/s Tata Sponge Limited | Prof. Brahma Deo | SMMME | 34.98 | 1 year | 15-Nov-18 | 14-Nov-19 | CP153 | Completed |
152 | Proof Checking of the design and drawings of 4 Nos. of RCC box culvert and suggestion of suitable soil stabilization for culvert No.4, at Biju Patnaik International Airport, Bhubaneswar | M/s Airports Authority of India, Bhubaneswar | Dr. S R Dash | SIF | 3.54 | 2 months | 29-Nov-18 | 29-Jan-19 | CP152 | Completed |
151 | Technicqal Scrutiny of 60m Box oushing section of underpass | Tata Steel Ltd | Dr. S R Dash | SIF | 2.21 | 1 month | 15-Nov-18 | 15-Dec-18 | CP151 | Completed |
150 | Evaluation of composite cements of Konark and Dalmia | Dalmia Cement Ltd | Dr. Dinakar Pasla | SIF | 1.38 | 1& 1/2 month | 13-Aug-18 | 27-Sep-18 | CP150 | Completed |
149 | Design and testing smart audio processing and communication systmes for voice processing and surveillance applications | Trijatta technologies (P) Ltd | Dr. M S Manikandan | SES | 2.87 | 6 months | 5-Nov-18 | 6-May-19 | CP149 | Completed |
148 | Monitor Settlements and effectiveness of the PVD-Package 2B construction of roadbed, station building, passenger amenities, Minor bridge, general electrical works in connection with new BR rail line from dumuka Km 57.00 to nuagaon km 68.300 on khurda road division of East coast railway in the State of Odisha | Rail Vikas Nigam Limited | Dr. B hanumatha Rao | SIF | 2.00 | 1 month | 8-Oct-18 | 7-Nov-18 | CP148 | Completed |
147 | Proof Checking of Designof Foundation and superstructure of video board at Kalinga Hockey Stadium at Bhubaneswar | SM Consultants | Dr. Sumanta Halder | SIF | 1.50 | 1 month | 28-Sep-18 | 28-Oct-18 | CP147 | Completed |
146 | Third party audit on fly ash generation and utilization of TTPs in Odisha for the year 2016-17 | SPCB | Dr. B Hanumatha Rao | SIF | 3.13 | 3 months | 20-Sep-18 | 20-Dec-18 | CP146 | Completed |
145 | Technical scrutiny of structural designs for the grade separator structure at Khandagiri Chowk on NH-16, Bhubaneswar, Odisha | National Highways Authority of India | Dr. S R Dash | SIF | 21.24 | 4 months | 15-Sep-18 | 15-Jan-19 | CP145 | Completed |
144 | Technical Scrutiny of launching scheme of six nos 30.50m open web girder of ROR bridge no. 37 of OPGC Ltd. | L&T Ltd | Dr. S R Dash | SIF | 2.66 | 1 month | 30-Aug-18 | 29-Sep-18 | CP144 | Completed |
143 | Third party quality assurance consultancy services for Kendriya Vidyalaya No.2, Sambalpur | Braithwaite Burn and Jessop Construction Company Ltd | Dr. Dinakar Pasla | SIF | 9.34 | 6 months | 4-Jul-18 | 2-Jan-19 | CP143 | Completed |
142 | Design Engineering service for the retrofitting works | ITC Ltd | Dr. Dinakar Pasla | SIF | 4.06 | 1 month | 25-Jul-18 | 24-Aug-18 | CP142 | Completed |
141 | Process control and optimization at Jindal Stainless Ltd, Jajpur,Odisha | Jindal Stainless Ltd | Prof. Brahma Deo | SMMME | 44.18 | 1 Year | 23-Jul-18 | 22-Jul-19 | CP141 | Completed |
140 | Design proof checking of five no of railway bridges of RITES Ltd in connection with construction of railway siding of NTPC Lara STTP | RITES Ltd | Dr. S R Dash | SIF | 10.47 | 5 months | 5-Nov-18 | 4-Apr-19 | CP140 | Completed |
139 | Vetting / proof checking of modification of boiler registration No-OR-1537 and OR-1539 | Directorate of factories and boilers, Odisha | Prof. S K Mahapatra | SMS | 5.22 | 6 weeks | 10-Jul-18 | 21-Aug-18 | CP139 | Completed |
138 | Distributed SDN controller with end to end security | Central Research Laboratory, Bharat Electronics Ltd | Dr. P L Bera | SES | 42.06 | 2 years 9 months | 29-Jun-18 | 27-Mar-21 | CP138 | Completed |
137 | Checking of design and drawing for the work construction of 7.5 MLD water treatment plant with ancillary structure at Ranibagicha, Sundargarh | Office of the Executive Engineer PH Dept., Rourkela | Dr. R R Dash | SIF | 1.03 | 1 month | 25-Jun-18 | 25-Jul-18 | CP137 | Completed |
136 | Design of compact/ miniature ultrasonic transducer | GE Oil & Gas (P) Ltd | Dr. Venugopal Arumuru | SMS | 2.95 | 2 months | 13-Jun-18 | 13-Aug-18 | CP136 | Completed |
135 | Person re-identification for video synopsis | Korea Institute of Science and Technology (KIST) | Dr. D P Dogra | SES | 18.54 | 9 months | 11-Jun-18 | 11-Mar-19 | CP135 | Completed |
134 | Proof checking of the design and drawings of substructure of railway road over bridge of RITES ROB 1Y, 1x2x24m composite girder | RITES Ltd | Dr. S R Dash | SIF | 2.07 | 2 months | 22-May-18 | 22-Jul-18 | CP134 | Completed |
133 | Proof checking of the design and drawings of substructure for 2 nos of major bridges (13 revised) and 113) in connection with Angul-Sukinda Railway New BG Link Project | Rail Vikas Nigam Ltd | Dr. S R Dash | SIF | 2.21 | 2 months | 23-May-18 | 23-Jul-18 | CP133 | Completed |
132 | UPV Test for primary sludge digestion at STP VI Bhubaneswar | Vatech Wabag Ltd | Dr. Dinakar Pasla | SIF | 1.84 | 3 months | 5-May-18 | 5-Aug-18 | CP132 | Completed |
131 | Electrical conductivity test in bricks | Jindal Steel and Power Limited | Dr. Dinakar Pasla | SIF | 2.35 | 2 months | 16-Feb-18 | 16-Apr-18 | CP131 | Completed |
130 | Inspection of defective works and submission of compliance report for construction of school building, staff quarters etc. at Kendriya Vidyalaya No. 2, Sambalpur, Odisha | Braithwaite Burn and Jessop Construction Company Limited | Dr. Dinakar Pasla | SIF | 3.22 | 1 day | 19-Feb-18 | 20-Feb-18 | CP130 | Completed |
129 | Vetting of Structural Design, drawing (Pre-Engineered Building), A/c The Samaja, Mancheswar, Bhubaneswar | LLOYD Insulations Ltd | Dr. Goutam Mondal | SIF | 3.78 | 1 month | 13-Mar-18 | 12-Apr-18 | CP129 | Completed |
128 | Reconstruction with geometric improvement of existing single/intermediate lane to 2 -lane with paved shoulders configuration from existing KM 92.880 to KM 121.550 of NH-125 in the state of Uttarkakhand on EPC mode, through engineering, procurement and construction (EPC) basis contract. | Shivalaya construction | Dr. P P Dey | SIF | 1.18 | 1 year | 2-Feb-18 | 1-Feb-19 | CP128 | Completed |
127 | Rehabilitation and upgradation to two-lane with paved shoulders from KM 531/250 to KM 597/946 (Kunkuri to CG/JH border section) of NH-78 in the state of Chhattisgarh under NHDP - IV through engineers, procurement & construction (EPC) basis. | Gawar-S.C.C. (JV), Rahtak, Haryana | Dr. P P Dey | SIF | 2.95 | 1 year | 2-Feb-18 | 1-Feb-19 | CP127 | Completed |
126 | Slope stability analysis for new BG Line from Nuagaon to Paradeep | ARSS Infrastructure | Dr. Sumanta Halder | SIF | 3.98 | 1 year | 28-Feb-18 | 27-Feb-19 | CP126 | Completed |
125 | Consultancy services for design of structural elements of MIG 29K and HAWK-AJT infrastructure at INS DEGA, Visakhapatnam | Subhadra Consultants | Dr. Goutam Mondal | SIF | 21.59 | 5 months | 3-Jan-18 | 2-Jun-18 | CP125 | Completed |
124 | Checking of safe bearing capacity of pile and suitable remedial measures for ROB at Ghantapada, Talcher | RITES Ltd | Dr. Sumanta Halder | SIF | 1.99 | 3 months | 3-Jan-18 | 3-Apr-18 | CP124 | Completed |
123 | Concrete cube testing for "Cyclone alert Communication System” in EWDS-Odisha Project for the Village situated in 6 districts viz., Kendrapara, Balasore, Bhadrak, Jagatsinghpur, Puri & Ganjam along coastal line of Odisha state | RG2SK Business Solution | Dr. Goutam Mondal | SIF | 0.73 | 5 months | 6-Apr-17 | 3-Sep-17 | CP123 | Completed |
122 | Improvement of Tara Tarini Temple Ring Road (Regarding with protection works- Hill top portion) in the district of Ganjam | Rural Works Dept., Govt. of Odisha | Dr. U C Sahoo | SIF | 3.54 | 2 months | 20-Dec-17 | 20-Feb-18 | CP122 | Completed |
121 | Development of Structural Grade Concretes for TG Deck Foundations | JK Papers Mills Limited | Dr. Dinakar Pasla | SIF | 1.77 | 3 weeks | 21-Nov-17 | 12-Dec-17 | CP121 | Completed |
120 | Proof checking of guided and fixed POT PTFE bearing | Rail Vikas Nigam Ltd, Rail Vihar | Dr. S R Dash | SIF | 1.48 | 3 weeks | 15-Dec-17 | 5-Jan-18 | CP120 | Completed |
119 | Vetting of bearing capacity calculations of mission shakti bhawan at pokhariput | IDCO | Dr. B hanumatha Rao | SIF | 1.84 | 3 weeks | 4-Oct-17 | 25-Oct-17 | CP119 | Completed |
118 | Design proff checking of six-buildings of RVNL work at Haridaspur-Paradeep New BG line | D K Construction | Dr. Goutam Mondal | SIF | 1.64 | 1 month | 20-Sep-17 | 20-Oct-17 | CP118 | Cancelled |
117 | Service as proof consultant for structural design components of proposed HL bridge over river biluakhai | Eastrn India Construction (P) Ltd | Dr. S R Dash | SIF | 7.38 | 2 months | 20-Sep-17 | 20-Nov-17 | CP117 | Completed |
116 | Proof Checking of 19m RCC T Beam ROB for railway siding Project of M/s Emami Cement Ltd. | M/s Emami Cement Ltd | Dr. S R Dash | SIF | 1.11 | 2 weeks | 1-Sep-17 | 15-Sep-17 | CP116 | Completed |
115 | Proof Checking of launching scheme of composite girders for ROB No. 438 of RVNL Sambalpur – Titlagarh Project | Rahee Infratech Ltd., West Bengal | Dr. S R Dash | SIF | 1.84 | 1 month | 31-Aug-17 | 30-Sep-17 | CP115 | Cancelled |
114 | Residual stress measurement in unrestrained and restrained double "V" joints | NMRL, DRDO | Dr. M M Mahapatra | SMS | 1.80 | 3 month | 31-Aug-17 | 30-Nov-17 | CP114 | Completed |
113 | Proof Checking of Design and Drawing of 14.2m steel semi through rail bridge girder | Sparsh Engineering Company (P) ltd | Dr. S R Dash | SIF | 0.59 | 2 weeks | 23-Aug-17 | 6-Sep-17 | CP113 | Completed |
112 | Mix Design for construction of ATC tower, Biju Patnaik International Airport, Bhubaneswar | Airport Authority of India | Dr. Dinakar Pasla | SIF | 1.88 | 2 month | 10-Jul-17 | 10-Sep-17 | CP112 | Completed |
111 | Mix Design for M25 and M30 Grade concretes | M/s Rathee, NBCC, Bhubaneswar | Dr. Dinakar Pasla | SIF | 2.39 | 2 month | 10-Jul-17 | 10-Sep-17 | CP111 | Completed |
110 | Geotechnical investigations on soil/rock samples | Vedanta Limited, Lanjigarh | Dr. B hanumatha Rao | SIF | 14.00 | 12-Jun-17 | CP110 | Completed | ||
109 | Evaluation of Terrazyme (A bioenzyme) stabilized roads constructed under PMGSY | Avijeet Agencies | Dr. U C sahoo | SIF | 25.00 | 2 years | 12-Jun-17 | 11-Jun-19 | CP109 | Completed |
108 | Examination of soundness of the intake well at Pankapal on the bank of river Bramhani, Dist: Jajpur | IDCO | Dr. Arindam Sarkar | SIF | 16.17 | 2 month | 30-May-17 | 30-Jul-17 | CP108 | Completed |
107 | Technical Support for application of cold mix Bitumen in Rural Roads | SAPCO Bitumen Company Ltd | Dr. U C sahoo | SIF | 30.00 | 3 years | 25-Apr-17 | 24-Apr-20 | CP107 | Completed |
106 | Designing of video synopsys algorithms for visual surveillance | Korea Institute of Science and Technology | Dr. Debi Prosad Dogra | SES | 40.39 | 2 years | 26-Apr-17 | 25-Apr-19 | CP106 | Completed |
105 | Design and drawing of minor bridges of RVNL proof checking | Rail Vikas Nigam Ltd. | Dr. S R Dash | SIF | 8.63 | 4 month | 12-Apr-17 | 12-Aug-17 | CP105 | Completed |
104 | Mix Design of cement treated base/ sub-base for PMGSY road in Odisha | Rural Works Dept., Govt of Odisha | Dr. U C sahoo | SIF | 94.85 | 2 month | 20-Mar-17 | 20-May-17 | CP104 | Completed |
103 | Proof checking of launching scheme of composite girders for ROB no 439 A and 423A of RVNL Sambalpur Titlagarh Project | Rahee Infratech Ltd, West Bengal | Dr. S R Dash | SIF | 1.15 | 2 week | 5-Apr-17 | 19-Apr-17 | CP103 | Completed |
102 | Vetting/ Proof checking of refrigeration for 3000 MT and 5000 MT | Engeering Projects (India) Ltd | Prof. S K Mahapatra | SMS | 3.59 | 3 week | 6-Apr-17 | 27-Apr-17 | CP102 | Completed |
101 | Strategies to counter energy imbalances in an aluminium reduction cell with an insert in the cathode collector bar | Tata International Ltd | Dr. Randhir Singh | SMMME | 1.27 | 6 month | 22-Mar-17 | 20-Sep-17 | CP101 | Completed |
100 | Proof checking of structural items of Rambili Project | M/s Suvadra Consultant | Dr. S R Dash | SIF | 14.95 | 4 month | 18-Mar-17 | 18-Jul-17 | CP100 | Completed |
99 | Vetting of second floor structure of CESU building for additional load | IDCO, BBSR | Dr. B hanumatha Rao | SIF | 1.87 | 2 month | 6-Mar-17 | 6-May-17 | CP099 | Completed |
98 | Dyke height raising of fly ash pond | Vedanta Limited, Lanjigarh | Dr. B hanumatha Rao | SIF | 6.74 | 2 month | 1-Mar-17 | 1-May-17 | CP098 | Completed |
97 | Characterization of soils treated with Zydex products for its use in PMGSY Roads | Zydex Industries (P) Ltd | Dr. U C sahoo | SIF | 2.30 | 2 month | 1-Mar-17 | 1-May-17 | CP097 | Completed |
96 | Mix Design for WMM & GSB with optimum utilisation of granulated slag | Tata Steel Ltd., Kalinga nagar | Dr. U C Sahoo | SIF | 1.15 | 1 week | 9-Feb-17 | 16-Feb-17 | CP096 | Completed |
95 | Accretion control to increase the sponge iron production to the target annual capacity of 390000Mt. | Tata Sponge Iron Ltd | Prof. Brahma Deo | SMMME | 13.11 | 1.5year | 15-Mar-17 | 13-Sep-18 | CP095 | Completed |
94 | Proof checking of major bridge @Ch 1+445 of NH-149 pallahara to pitiri section, Odisha | RKD Construction Pvt. Ltd | Dr. S R Dash | SIF | 2.88 | 1 month | 26-Jan-17 | 25-Feb-17 | CP094 | Completed |
93 | Review of science hopper lab in the class program - Physics | Science Hopper Education (P) Ltd., Bangalore | Dr. S Chatterjee | SBS | 0.67 | 3 month | 20-Jan-17 | 20-Apr-17 | CP093 | Completed |
92 | Vetting of design and drawings of aranya bhavan 6th floor conference room | IDCO | Dr. B Hanumatha Rao | SIF | 1.50 | 2 week | 2-Jan-17 | 16-Jan-17 | CP092 | Completed |
91 | Structural stability for the building with revised loading conditions of 2nd floor level with its retrofitting actions | NBCC (I) Ltd. | Dr. Sumanta Halder | SIF | 8.00 | 3 month | 9-Jan-17 | 9-Apr-17 | CP091 | Completed |
90 | Vetting of the AFS Hanger at Bagdogra, super structure drawing (Steel Structure) | M/s MES Engineering, Kolkata | Dr. Goutam Mondal | SIF | 1.75 | 1 month | 30-Jan-16 | 29-Feb-16 | CP090 | Completed |
89 | Third party audit on the fly ash generation & utilization by TPPs in Odisha for the year 2015-16 | M/s State Pollution control Board, Odisha | Dr. B hanumatha Rao | SIF | 2.59 | 2 week | 17-Feb-17 | 3-Mar-17 | CP089 | Completed |
88 | Proof Checking of Design Splice & its adequacy by M/s S M Consultancy for 30m FOB girder | Rail Vihar Nigam Ltd. Waltair | Dr. S R Dash | SIF | 0.41 | 2 week | 9-Jan-17 | 23-Jan-17 | CP088 | Completed |
87 | Monitoring and quality assurance of construction of international standard sport climbing wall at kalinga stadium, BBSR | Outdoor School | Dr. Sumanta Halder | SIF | 7.10 | 3 months | 9-Jan-17 | 9-Apr-17 | CP087 | Completed |
86 | Proof checking of design and drawing of substructure in connection with Angul-Sukinda for 16 nos of major bridges of RVNL | Rail Vihar Nigam Ltd. BBSR | Dr. S R Dash | SIF | 11.00 | 6 months | 9-Jan-17 | 10-Jul-17 | CP086 | Completed |
85 | Testing pf CC cores of RE Facia Panel | NHAI, PIU-BBSR | Dr. U C Sahoo | SIF | 1.73 | 1 week | 2-Jan-17 | 9-Jan-17 | CP085 | Completed |
84 | Construction of new road at the missing link portion of NH81 along the approved alignment between Harischandrapur and eastern approach of kalindri - bridge from Km 46.550 to km59.697 in the district of Malda, West Bengal on EPC mode | Dynamic Projects (P) Ltd | Dr. P P Dey | SIF | 2.30 | 1 year | 21-Dec-16 | 20-Dec-17 | CP084 | Completed |
83 | Proof checking of design and drawings of substructure for 6 nos of major bridges of RVNL | Rail Vikas Nigam Ltd | Dr. S R Dash | SIF | 2.16 | 1.5 month | 15-Nov-16 | 30-Dec-16 | CP083 | Completed |
82 | Quality test of Railway track stone (Gudiakateni & Chandikhol) | Jyoti Construction | Dr. U C sahoo | SIF | 0.30 | 1 week | 22-Nov-16 | 29-Nov-16 | CP082 | Completed |
81 | Development of structural grade concretes utilizing Iron slag as sand replacements (Tata Steel, Jaipur, Odisah) | Tata Steel, Kalinga Nagar | Dr. Dinakar Pasla | SIF | 5.74 | 3 month | 21-Oct-16 | 21-Jan-17 | CP081 | Completed |
80 | Proof checking of design and drawing of substructure and foundation abutment-2 of bridge no -76 | Rail Vikas Nigam Ltd | Dr. S R Dash | SIF | 0.86 | 2 weeks | 17-Oct-16 | 31-Oct-16 | CP080 | Completed |
79 | Vetting of Structural design and drawing of the Dinjan Hanger foundation | LLOYD Insulations Ltd | Dr. Goutam Mondal | SIF | 0.30 | 1 month | 21-Jun-16 | 21-Jul-16 | CP079 | Completed |
78 | Analysis and Implementation of non chronological video synopsis and indexing | Indo Korea Science and Technology Center, Bangalore | Dr. Debi Prosad Dogra | SES | 15.00 | 1 year | 4-Oct-16 | 3-Oct-17 | CP078 | Completed |
77 | Technical support on pile design in L iquefiable soils for the building at the Sewage Treatment Plant (Tunasan STP) | Vatech Wabag Ltd | Dr. S R Dash | SIF | 2.88 | 2 weeks | 26-Sep-16 | 10-Oct-16 | CP077 | Completed |
76 | Proof checking of structural calculation/ drawing for proposed construction of JNV/ Nayagarh (Phase-B) works at Odisha | Buildsol, Architectural & Engineering Consultants | Dr. S R Dash | SIF | 0.65 | 2 weeks | 17-Sep-16 | 1-Oct-16 | CP076 | Completed |
75 | Widening and strengthening of Khunti-Torpa-Kolebira Road (from 0.00 km to 82.055 km) to 2-lane with paved shoulder | Gawar-S.C.C. (JV), Rahtak, Haryana | Dr. P P Dey | SIF | 3.52 | 1.6 year | 9-Sep-16 | 16-Apr-18 | CP075 | Completed |
74 | Mix design for glass fibre reinforced concrete for IMDC Mancheswar, Bhubaneswar | NBCC, Bhubaneswar | Dr. Dinakar Pasla | SIF | 1.64 | 3 month | 17-Aug-16 | 17-Nov-16 | CP074 | Completed |
73 | Vetting of feasibility study of pre-treatment of coke oven and by-product plant effluent in coal gasification process units for recovery of Phenol and Ammonia | Jindal Steel and Power Limited | Dr. P Bhunia | SIF | 5.75 | 1.5 month | 11-Aug-16 | 25-Sep-16 | CP073 | Completed |
72 | Proof checking of design and drawing of road under bridge (RUB) No-68 of RVNL | Rail Vikas Nigam Ltd, Rail Vihar | Dr. S R Dash | SIF | 0.36 | 1 month | 9-Aug-16 | 8-Sep-16 | CP072 | Completed |
71 | Widening and strengthening from km 94.000 to 131.000 of NH-133 in the state of Jharkhand through EPC Basis contract | Gawar-S.C.C. (JV), Rahtak, Haryana | Dr. P P Dey | SIF | 1.59 | 1 year | 1-May-16 | 30-Apr-17 | CP071 | Completed |
70 | Mix Design for M25 for Mahanadi Institute of medical sciences and research at Talcher , Angul, Odisha | NBCC, Talcher | Dr. Dinakar Pasla | SIF | 3.11 | 3 month | 27-Jul-16 | 27-Oct-16 | CP070 | Completed |
69 | Study of Probabilities and changes in frequencies and intensities of tropical cyclones and associated wind and rainfall over Puri district of Odisha in climate change projection [Period: 1891-2015] | Institute for Social and Environmental Transition-International (ISET-I) | Prof. U C Mohanty | SEOCS | 4.02 | 3 month | 28-Jul-16 | 28-Oct-16 | CP069 | Completed |
68 | Mix Design of M30 Grade Concrete for ITC Hotel | Prime Techno Engineers (P) Ltd. | Dr. Dinakar Pasla | SIF | 0.45 | 1 month | 2-Jul-16 | 1-Aug-16 | CP068 | Completed |
67 | Endorsement of the estimation of production quantities of sponge iron and steel billets of Maa Mahamaya Industries Ltd, R.G. Peta in the years 2006-07, 2007-08 and 2008-09 from the charge mix used | Maa Mahamaya Industries Ltd | Dr. V Pandu Ranga | SMS | 1.20 | 1 Week | 7-Jul-16 | 14-Jul-16 | CP067 | Completed |
66 | Proof checking of design and drawing for 2 nos of S&T Cabin building for M/S NTPC at Kaniha | RITES Ltd | Dr. S R Dash | SIF | 0.72 | 2 week | 17-Jun-16 | 1-Jul-16 | CP066 | Completed |
65 | Proof checking of design and drawing of substructure for major bridges no 115 and 131 | Rail Vikas Nigam Ltd, Rail Vihar | Dr. S R Dash | SIF | 1.15 | 1 month | 21-Jun-16 | 21-Jul-16 | CP065 | Completed |
64 | Technical and function test of Gagan enabled GPS PDAs | Conservator for Forest, GIS, Aranya Bhawan | Dr. P R Sahu | SES | 1.95 | 1.5 month | 10-May-15 | 24-Jun-15 | CP064 | Completed |
63 | Video analysis algorithms to detect unusual behaviour in crowd and traffic | outdu Media Tech Pvt. Ltd. | Dr. Debi Prosad Dogra | SES | 6.52 | 3 months | 15-Jun-16 | 15-Sep-16 | CP063 | Completed |
62 | Design and developing a portable wireless noise level and vibration monitors | Pentagon Rugged Systems India (P) Ltd | Dr. M S Manikandan | SES | 1.04 | 3 months | 15-May-16 | 15-Aug-16 | CP062 | Completed |
61 | Design and developing a portable wireless air quality monitor | Pentagon Rugged Systems India (P) Ltd | Dr. M S Manikandan | SES | 2.44 | 3 month | 15-May-16 | 15-Aug-16 | CP061 | Completed |
60 | Testing of Panels for energy absoption test | ILFS SIF | Dr. Dinakar Pasla | SIF | 2.86 | 1 month | 23-May-16 | 22-Jun-16 | CP060 | Completed |
59 | Inspection of quality control laboratory | Maa Mahamaya Industries Ltd | Dr. V Pandu Ranga | SMS | 1.19 | 1 week | 6-May-16 | 13-May-16 | CP059 | Completed |
58 | Implementation of water quality monitoring and management system | Pentagon Rugged Systems India (P) Ltd | Dr. M S Manikandan | SES | 1.49 | 2 months | 15-Apr-16 | 15-Jun-16 | CP058 | Completed |
57 | Testing of light weight aggregates (LWAs) in various concrete grades and the physical and chemical testing of the aggregates and also the structural load behaviour of the LWA concretes | Jindal Steel and Power Limited | Dr. Dinakar Pasla | SIF | 5.64 | 3 months | 12-May-16 | 12-Aug-16 | CP057 | Completed |
56 | Proof Checking of Design and Drawing of Substructure of Railway Bridge of RVNL | Rail Vikas Nigam Ltd, Rail Vihar | Dr. S R Dash | SIF | 0.86 | 1 week | 8-Apr-16 | 15-Apr-16 | CP056 | Completed |
55 | Vetting of structure and superstructure of sports climbing facility at Kalinga Stadium confirming to IFSC standard | Outdoor School | Dr. Sumanta Halder | SIF | 4.09 | 3 months | 10-Mar-16 | 10-Jun-16 | CP055 | Completed |
54 | Stability study of the ash filled area | Vedanta Limited | Dr. B hanumatha Rao | SIF | 3.14 | 1 year | 10-Feb-16 | 8-Feb-17 | CP054 | Completed |
53 | C/C++ implementation with adequate GUI for sparsity based abnormal event detection | Indo Korea Science and Technology Center, Bangalore | Dr. Debi Prosad Dogra | SES | 7.00 | 6 months | 10-Feb-16 | 10-Aug-16 | CP053 | Completed |
52 | C/C++ implementation with adequate GUI for temporal analysis of motif mixtures using Dirichlet process | Indo Korea Science and Technology Center, Bangalore | Dr. Debi Prosad Dogra | SES | 8.00 | 6 months | 10-Feb-16 | 10-Aug-16 | CP052 | Completed |
51 | Design and Drawing for Katekela Lagoon-2 ash pond | Vedanta Limited | Dr. B hanumatha Rao | SIF | 8.19 | 1 Year | 30-Oct-15 | 28-Oct-16 | CP051 | Completed |
50 | Strenghthening and Widening/ Reconstruction of Dumka Masalia-Nala upto West Bengal Border Road lane with paved shoulder under EPC Mode (55 km) | Barbrik_RCPL(JV) | Dr. P P Dey | SIF | 2.36 | 1year | 30-Oct-15 | 29-Oct-16 | CP050 | On-going |
49 | Design of experimental road using fly ash | Sesa Sterlite Limited | Dr. B hanumatha Rao | SIF | 3.08 | 2 months | 30-Oct-15 | 30-Dec-15 | CP049 | Completed |
48 | Technical Evaluation of cement concrete roads in Odisha | Planning & Coordination Dept., Govt. of Odisha | Dr. U C sahoo | SIF | 28.16 | 8 months | 30-Oct-15 | 30-Jun-16 | CP048 | Completed |
47 | Technical Scrutiny of irrigation road proposal under IRC & IS | Water Reseources Dept., Govt. of Odisha | Dr. U C sahoo | SIF | 4.26 | 3 month | 13-Nov-15 | 13-Feb-16 | CP047 | Completed |
46 | Vetting of schematic drawing along with transmission loss calculation for 6.6KV/ 415V OHDC line | Megha Engineering & SIF Ltd. | Dr. S B Karanki | SES | 0.33 | 2 weeks | 30-Sep-15 | 14-Oct-15 | CP046 | Completed |
45 | Modelling of the Cathode assembly in Aluminium reduction cell | Tata International Ltd | Dr. Randhir Singh | SMMME | 0.74 | 3 month | 16-Sep-15 | 16-Dec-15 | CP045 | Completed |
44 | Preparation of DPR for the proposed National Institute for New Energy & Innovation at Bhubaneswar | Ministry of New Renewable Energy, Govt. of India | Prof. N C Sahoo | SES | 5.00 | 14-Oct-15 | CP044 | Completed | ||
43 | Improvement and upgradation of two lane with paved shoulder configurationof Koderma-Domchanch-Khorimahua-Jamua Road (SH-13) under EPC mode in Jharkhand | On behalf of NIT Durgapur as external expert RKS Constuction (P) Ltd. Ranchi | Dr. P P Dey | SIF | 4.00 | 2 year | 27-Jul-15 | 26-Jul-17 | CP043 | Completed |
42 | Conducting Mix Design for M50 for NBCC Bhubaneswar | NBCC Ltd | Dr. Dinakar Pasla | SIF | 1.33 | 3 month | 11-Jul-15 | 11-Oct-15 | CP042 | Completed |
41 | Geotechnical investigations on soil/rock samples | NBCC Ltd | Dr. B hanumatha Rao | SIF | 1.20 | 1 week | 24-Jun-15 | 1-Jul-15 | CP041 | Completed |
40 | Process optimization studies on leaching of high ash coal to produce low ash coal | Tata Steel Ltd | Prof. N P H Padmanabhan | SMMME | 6.75 | 7 month | 15-May-15 | 11-Dec-15 | CP040 | Completed |
39 | Survey on process study of CPC and EPC of Amritesh Industries Pvt. Ltd, Angul | Amritesh Industries Pvt. Ltd. | Dr. Akhilesh Barve | SMS | 0.40 | 1 Week | 24-Jun-15 | 1-Jul-15 | CP039 | Completed |
38 | Testing of Ballast from Baghua Querry | Maa Chandi Stone Crushing | Dr. S R Dash | SIF | 0.17 | 1 week | 5-Jun-15 | 12-Jun-15 | CP038 | Completed |
37 | Surge analysis for 1000mm Dia water rising main at Jajpur | IDCO | Dr. Arindam Sarkar | SIF | 1.90 | 1 month | 27-May-15 | 26-Jun-15 | CP037 | Completed |
36 | Proof checking of srtructural design nad drawing | Hindustan steel works construction Ltd. | Dr. S R Dash | SIF | 0.43 | 2 weeks | 12-May-15 | 26-May-15 | CP036 | Completed |
35 | Survey of capacity assessment of Amritesh Industries Pvt. Ltd. | Amritesh Industries Pvt. Ltd. | Dr. V Pandu Ranga | SMS | 0.27 | 1 week | 6-May-15 | 13-May-15 | CP035 | Completed |
34 | Design and analysis for making rural road about 1 km by using JK Paper Mills fly ash | JK Papers Mills Limited | Dr. B Hanumatha Rao | SIF | 2.85 | 1.5 month | 20-Apr-15 | 4-Jun-15 | CP034 | Completed |
33 | Assessment of structural safety of construction of balance six floor of the IDCOL corporate office building, BBSR | IDCO | Dr. Sumanta Halder | SIF | 12.64 | 3 month | 9-Apr-15 | 9-Jul-15 | CP033 | Completed |
32 | Testing of materials and conducting design mix M-25,M-30 & M-40 in connection with construction of commercial cum residential complex | National Building construction corporation Ltd. | Dr. P Bhunia | SIF | 4.38 | 9-Apr-15 | CP032 | Completed | ||
31 | Report on Dolomite and its usage in sponge Iron production | Ganesh Sponge (P) Ltd. | Dr. Soobhankar Pati | SMMME | 0.30 | 1 day | 17-Mar-15 | 18-Mar-15 | CP031 | Completed |
30 | Opinion regarding the dri reduction furnace at JSPL plant Angul | Kazstroy Services SIF Pvt. Ltd | Dr. Dinakar Pasla | SIF | 2.81 | 3 month | 18-Mar-15 | 18-Jun-15 | CP030 | Completed |
29 | Assessing the soil for earth work construction | IVRCL Limited | Dr. B hanumatha Rao | SIF | 0.53 | 1 Week | 12-Mar-15 | 19-Mar-15 | CP029 | Completed |
28 | Testing of AAC Blocks | Overtop marketing (P) Ltd. | Dr. Dinakar Pasla | SIF | 3.07 | 2 month | 12-Mar-15 | 12-May-15 | CP028 | Completed |
27 | Testing of AAC Blocks | Fast Build Blocks Pvt. Ltd | Dr. Dinakar Pasla | SIF | 0.77 | 2 month | 13-Mar-15 | 13-May-15 | CP027 | Completed |
26 | Vetting/checking of the project report prepared by CEMCPL for Ordnance Factory, Ambajhari, Nagpur | Centre for Envotech and Management Consultancy (P) Ltd | Dr. R R Dash | SIF | 1.40 | 1 month | 30-Jan-15 | 1-Mar-15 | CP026 | Completed |
25 | Robotic application in boiler NDT assessment | OMS Power Training and research Institute | Dr. V Pandu Ranga | SMS | 3.29 | 2 months | 7-Jan-15 | 7-Mar-15 | CP025 | Completed |
24 | Testing of Fibre shorcrete panels for energy absorption test | Leighton India Contractors (P) Ltd | Dr. Dinakar Pasla | SIF | 4.68 | 3 months | 4-Dec-14 | 4-Mar-15 | CP024 | Completed |
23 | Design and stability analysis of an embankment for new BG rail line from Haridaspur to Paradeep in the Khurda district Odisha | Tracks & Tower Infratech (P) Ltd | Dr. B Hanumatha Rao | SIF | 3.65 | 1 month | 2-Dec-14 | 1-Jan-15 | CP023 | Completed |
22 | Testing of Fibre shorcrete panels for energy absorption test | Leighton India Contractors (P) Ltd | Dr. Dinakar Pasla | SIF | 5.26 | 3 months | 6-Nov-14 | 6-Feb-15 | CP022 | Completed |
21 | Issue of Check Proof Certificate and Procedure for the rectification of FOB along with necessary drawing regarding | McML-ECI(JV) | Dr. S R Dash | SIF | 1.26 | 2 Weeks | 16-Sep-14 | 30-Sep-14 | CP021 | Completed |
20 | Assessment of High Compressibility of cut spoil | Tracks & Tower Infratech (P) Ltd | Dr. B hanumatha Rao | SIF | 1.26 | 1 month | 16-Sep-14 | 16-Oct-14 | CP020 | Completed |
19 | Widening & Strengthening of Bhawanipatna-Gunupur-Kasipur Road (SH-44) to 2 Lane without paved shoulder from Km 0/000 to 13/000 & Km 42/940 to Km 48/840 on EPC mode in the district of Kalahandi | Office of the Executive Engineer Koraput (R&B) Division | Dr. B hanumatha Rao | SIF | 0.50 | 1 month | 12-Sep-14 | 12-Oct-14 | CP019 | Completed |
18 | Vetting of structural Design and Drawing for the Construction of L.I.G and L.M.I.G housing Complex along with Commercial Complex at Kalinga Nagar Zone- K4 | BDA | Dr. S R Dash | SIF | - | - | 13-Aug-14 | CP018 | Cancelled | |
17 | Impact Assessment study of city bus services operational under JnNURM | Housing and Urban Development Department, Govt of Odisha | Dr. Debasis Basu | SIF | 6.98 | 4 month | 13-Aug-14 | 13-Dec-14 | CP017 | Completed |
16 | Proof Checking of POT cum PTFE Bearing | Bhubaneswar Expressways Pvt. Ltd | Dr. Dinakar Pasla | SIF | 1.01 | 1 month | 30-Jul-14 | 29-Aug-14 | CP016 | Completed |
15 | Co-operation and expert advice for improvement of short and extended range (monthly scale) prediction of rainfall in the tropics | RIMES | Prof. U C Mohanty | SEOCS | 10.00 | 1 Year | 18-Jun-14 | 17-Jun-15 | CP015 | Completed |
14 | Design and testing aerated autoclaved fly concrete blocks (AAC) | Fast Build Blocks Pvt. Ltd | Dr. Dinakar Pasla | SIF | 1.18 | 1 month | 10-May-14 | 9-Jun-14 | CP014 | Completed |
13 | Consultancy for investigation in ARC, Charbatia | Airports Authority of India, Biju Pattanaik Airport | Dr. Dinakar Pasla | SIF | 13.49 | 3 month | 16-May-13 | 16-Aug-13 | CP013 | Completed |
12 | Proof checking of design and drawing of three no. box bridges under Railway loading in connection with construction of railway siding to serve Koderma Thermal Power Plant (2x500MW) of DVC | RITES Ltd | Prof. S.C. Dutta | SIF | 3.79 | 3 month | 14-Nov-12 | 14-Feb-13 | CP012 | Completed |
11 | Database for Principal Technical Agency & State Technical Agency for states of Jharkhand and Odisha | NRIDA | Dr U C Sahoo | SIF | 42.72 | 30-Aug-12 | CP011 | Completed | ||
10 | Design of weighbridge & moveable floor crane | DS Systems | Dr. S N Panigrahi | SMS | 1.16 | 10 months | 14-Jun-12 | 10-Apr-13 | CP010 | Completed |
9 | Design of two number of 220KV transmission line tower foundations between Kantapalli to Hindalco in the mahanadi river | Hindalco Industries Ltd. | Dr. Arindam Sarkar | SIF | 7.18 | 8 months | 11-Apr-12 | 11-Dec-12 | CP009 | Completed |
8 | House hold energy consumption survey-2012 | WMG | Dr. S R Samantaray | SES | 1.20 | 1 Year | 24-Mar-12 | 23-Mar-13 | CP008 | Completed |
7 | Proof Checking of design of pile foundations for location no. 16A and 24 of 220 KV transmission line tower from Bidanasi ( Cuttack) near the bank of Kathajodi to Nuapada (Cuttack) in the spill zone | Orissa Power Transmission Corporation Limited | Dr. Sumanta Halder | SIF | 2.27 | 1 month | 19-Oct-11 | 18-Nov-11 | CP007 | Completed |
6 | Vetting of structural analysis of design and drawing for the new residential complex at HAL Koraput | HAL | Prof. S.C. Dutta | SIF | 5.00 | 1 month | 18-Oct-11 | 17-Nov-11 | CP006 | Completed |
5 | Proof Checking of design of river bed pile foundation for location no. 10,12 & 15 of 220KV transmission line from Bidanasi to Cuttack grid substation | Orissa Power Transmission Corporation Limited | Dr. Sumanta Halder | SIF | 3.31 | 1 month | 31-May-11 | 30-Jun-11 | CP005 | Completed |
4 | Preparation of special Foundation for 220KV Tower for Two locations(158-c & 159) | Hindalco Industries Ltd. | Dr. Arindam Sarkar | SIF | 4.84 | 1 month | 6-May-11 | 5-Jun-11 | CP004 | Completed |
3 | Proof Checking od 3 Nos panel cabin building and 1 no. gate lodge/IBS Building for M/s. Nalco Angul | RITES Ltd | Dr. Dinakar Pasla | SIF | 0.60 | 3 months | 11-Oct-10 | 11-Jan-11 | CP003 | Completed |
2 | Remedial Measures for Horizontal and vertical Cracks Developed in the walls, floors, roof etc of ESI Hospital, Jaykaypur | ESI Corporation | Dr. Dinakar Pasla | SIF | 3.95 | 3 months | 6-Sep-10 | 6-Dec-10 | CP002 | Completed |
1 | Vetting of the design of lighting masts and their foundations in connections with commissioning of lighting systems of wankahade stadium | Bajaj Electricals Ltd. | Prof. S.C. Dutta | SIF | 1.10 | 1 month | 17-Sep-09 | 17-Oct-09 | CP001 | Completed |